Slashdot Mirror


Software Defects - Do Late Bugs Really Cost More?

ecklesweb asks: "Do software defects found in later phases of the software development cycle REALLY cost THAT much more than defects found in earlier phases? Does anyone have any empirical data (not anecdotal) to suggest that this logarithmically increasing cost idea is really true? That is the question I use whenever I want to tick off a trainer. Seriously, though, it seems an important question given the way this 'concept' (or is it a myth?) drives the software development process."

"If you're a software engineer, one of the concepts you've probably had driven into your head by the corporate trainers is that software defects cost logarithmically more to fix the later they are found in the software development life cycle (SDLC).

For example, if a defect is found in the requirements phase, it may cost $1 to fix. It is proffered that the same defect will cost $10 if found in design, $100 during coding, $1000 during testing.

All of this, to my knowledge, started by Barry Boehm in papers[1]. In these papers, Mr. Boehm indicates that defects found 'in the field' cost 50-200 times as much to correct as those corrected earlier.

That was 15 years ago, and as recently as 2001 Barry Boehm indicates that, at least for small non-critical systems, the ratio is more like 5:1 than 100:1[2].

[1] - Boehm, Barry W. and Philip N. Papaccio. 'Understanding and Controlling Software Costs,' IEEE Transactions on Software Engineering, v. 14, no. 10, October 1988, pp. 1462-1477

[2] - (Beohm, Barry and Victor R. Basili. 'Software Defect Reduction Top 10 List,' Computer, v. 34, no. 1, January 2001, pp 135-137.)"

4 of 125 comments (clear)

  1. Thigs they don't tell you ... by Pogue+Mahone · · Score: 4, Interesting
    The bugs might be cheaper to fix, but they cost a lot more to find.

    At any stage, you can only find bugs that are introduced at or before that stage. So while fixing a requirements bug in the coding phase might be more expensive than fixing it during the requirements phase, fixing a coding bug during the requirements phase is a tricky operation that I'll leave as an exercise for the reader :-)

    Of course, if you omit some of these phases completely, you won't introduce any bugs during them. That's why the JFDI(*) methodoloy is so popular.




    (*)Just F*cking Do It

    --
    Every bloody emperor has his hand up history's skirt [Peter Hammill/VdGG]
  2. Yes by Anonymous Coward · · Score: 3, Interesting

    Compare the cost of testing, then over-the-air updates to a set of mobile phones & associated risk management
    to
    the cost of just building and shipping new code
    that has yet to undergo testing or launch.

    To give you an idea, managing the testing and upgrading over-the-air softare in mobile phones can become a new project in its own right with all the associated monitoring and overheads.

    Fixing the bug of a pre-launch project can be a 1 minute job.

  3. Also, bugs take $$$, who should pay? and ethics? by Frobnicator · · Score: 5, Interesting
    Similar experience for me, too. It is anecdotal evidence and not proof of the costs(let us not confuse the two). Now some questions to add to your observations: Should the company be liable for an engineer's errors (as is normally done in business)? Or should the individual or team be liable?

    Most recently I've been tracking down an error in our system. After nearly a month of trying various things, I found the problem of an error. In this case, two years ago the hardaware engineer building the FPGA and DSP programs didn't bother to fix the [relatively simple] design problem. Rather than give all communications the same format, a few commands differ substantially from all others (different responses in certain circumstances, for example).

    The problem made it into the PC software that interfaces with the board. The problem is documented in several [maybe 20?] bugs of the software that works between the PC and the external device. The problem is documented in at least 50 bugs in a port of that PC software. It has been in production for several years, and implemented by external companies (which I feal sorry for, due to the complexity of the communications bug).

    Now we're working on a completely new FPGA/DSP board to replace the earlier board. Design changes prevent us from directly implementing the bug in the new design, although otherwise the communication protocols are the same. Implementing the same malformed communications will mean breaking the simple straightforward design and carefully implementing a set of 'design exceptions' (read: 'bugs').

    It would have taken one engineer an hour or so to fix this thing when they first saw it. It would have taken both teams a few days to fix it when writing the PC to DSP interface (~1 FTE month). It would have taken a few weeks to fix it when writing the port, requiring changes to the PC software and the DSP (~1 FTE year). If we choose to fix the error now, it will probably result 2+ FTE years of work to just fix everything, and more time for regression testing every old peice of software for this one bug. If we choose to leave it in, we will devote at least that much time in evaluating, implementing, and testing the old errors. Not to mention the continued maintenence work when the eventual bugs are found in the new board.

    Now we're forced with a tough financial decision: do we spend a month or more carefully re-creating and testing the 'design exceptions', (probably 3-5 FTE years in total) or do we do it 'the right way' and break both our own and our customers' software? (again, several FTE years, but potentially loosing faith with the customers.)

    This particular bug could have been prevented by about $50 of work. It has now cost the company tens of thousands of dollars, and will probably cost a few hundred thousand before all is said and done.

    Now, lets throw some financial ethics into the $50 --> $5,000 --> $50,000 --> $500,000+ problem: The engineer was in a hurry to fix the problem before a company imposed deadline. Is that engineer responsible for the enormous financial cost? If so, how much? If not, why not? It can be argued that his negligence cause a half-million dollars in damages. It can be argued that the engineer was responsible for $50 but the team was responsible for allowing it to grow. It can be argued that this is a regular business cost due to falibility of engineers' designs.

    This begs the question:

    How responsible are any of us for the errors we introduce?

    frob

    --
    //TODO: Think of witty sig statement
  4. Larry Ellison's Solution to Version 2.0 Problem by joneshenry · · Score: 4, Interesting

    From what I have read, Oracle's founders had the best solution to the problem of customers holding off buying until version 2.0: "This first Oracle was named version 2 rather than version 1 because the fledgling company thought potential customers were more likely to purchase a second version rather than an initial release."