Generator Delays May Slow Data Center Projects
miller60 writes "The data center building boom is causing backlogs for new generator orders, with some companies reporting delivery delays of up to a year for new 2,000kw units, which are the current standard for mission-critical facilities. Generator availability is 'the No. 1 thing that will drive your construction schedules,' according to Equinix, which is building centers in three major markets. 'This will be a big issue for the next wave of data center builds,' says another industry executive. Used generators and smaller units tend to be more available than the 2 megawatt units, but companies targeting the enterprise sector may be wary of relaying on used units or smaller generators than those powering competing facilities."