Building a Data Center In 60 Days
miller60 writes "The facilities team at Australia's Pipe Networks is down to the wire in its bid to complete a data center in 60 days. And in an era when many major data-center projects are shrouded in secrecy, these guys are putting the entire effort online, with daily updates and photos on the company blog, a live webcam inside the facility, a countdown timer, and a punch-list of key tasks left to finish. Their goal is to complete the job by Friday morning eastern US time."
In Australia, its a datacentre. Comparative to the number of people in Au & the connections within Australia & to the rest of the world, its pretty big.
We only have two major cables out of Australia & capacity on them to the US costs hundreds of dollars a megabit/month.