Slashdot Mirror


Judge Tosses Telco Suit Over City-Owned Network

tsa sends along news of the city of Monticello, Minnesota, which was sued by their local telco, Bridgewater Telephone Company, because the city chose to build a fiber optics network of their own. The judge dismissed their complaint of competition by a governmental organization. Quoting: "The judge's ruling is noteworthy for two things: (1) the judge's complete dismissal of Bridgewater Telephone Company's complaint and (2) his obvious anger at the underfunding of Minnesota's state courts. Indeed, the longest footnote in the opinion is an extended jeremiad about how much work judges are under and why it took so long to decide this case."

2 of 281 comments (clear)

  1. Government could have fought back by MobyDisk · · Score: 4, Interesting

    I imagine that the telco must have had to get permits to lay their own fiber. The government could have blocked those requests until the result of the case was decided, thus cancelling-out the telco's attempt to delay the government and get a head start. I wonder why this didn't happen?

    1. Re:Government could have fought back by Anonymous Coward · · Score: 4, Interesting

      Because blocking legitimate requests for development is generally not allowed. I know California has strict time limits for certain actions, and if no action is taken within a given period, there is the possibility for legal repercussions.

      In other words, a jurisdiction can't just say "we don't like it, go away" or "wait until we have what we want." There have to be actual grounds to put something on hold, or even more to deny a project all-together.