How Do You Accurately Estimate Programming Time?

itwbennett writes "It can take a fairly stable team of programmers as long as six months to get to a point where they're estimating programming time fairly close to actuals, says Suvro Upadhyaya, a Senior Software Engineer at Oracle. Accurately estimating programming time is a process of defining limitations, he says. The programmers' experience, domain knowledge, and speed vs. quality all come into play, and it is highly dependent upon the culture of the team/organization. Upadhyaya uses Scrum to estimate programming time. How do you do it?"

1 of 483 comments (clear)

  1. Uhh, Scrum is not an estimation method by pclminion · · Score: 5, Interesting

    Scrum is a way of chunking development into well-defined portions. The idea of using Scrum to estimate time just doesn't make sense. Everything in Scrum takes the same amount of time. Two weeks. (Or one week, or whatever your sprint length is.) The difference is that long projects are implemented over multiple sprints, since obviously, not everything can be done in two weeks. So the estimate is not of how long it will take, but how many backlog items will be required in order to reach some known endpoint. Once the backlogs have been created and agreed upon by the team, estimating the necessary time becomes a matter of multiplication: 12 backlogs * 2 weeks = 24 weeks to finish this product.

    This makes you shift your thinking from "how long will it take to do all these things" to "how can I break this product development into chunks which each fit into a two-week period?" That's much easier than making wild-ass guesses about the time it takes to do something.