UPS Setup For a Small/Mid-Size Company?

An anonymous reader writes "We're a small company employing ~30 people and we are becoming increasingly reliant on virtual servers. Unfortunately, the hosts they are on don't have redundant power supplies because we simply don't have the capacity. We currently have one UPS per rack, which gives us about two minutes. This may have been enough time when they were put in — they've been there for some time — but it isn't really enough time to shut everything down in the event of a failure. Domain Controllers alone may take up to 15 minutes. So I'm looking at upgrading the UPSs to ones that would preferably give us around 15 minutes of breathing space and send an email or text alert when a failure is detected. Something that could trigger shutdowns automatically would also be nice. Of course cost is a key factor too. so given all of the above, what does Slashdot recommend?"

51 of 260 comments (clear)

  1. stationary bikes with alternator by Anonymous Coward · · Score: 3, Funny

    should serve 2 purpose - give you temp power and keeps your IT guys fit

    1. Re:stationary bikes with alternator by biryokumaru · · Score: 3, Informative

      This is a much better solution. Plus, it can melt your face!

      --
      When you're afraid to download music illegally in your own home, then the terrorists have won!
    2. Re:stationary bikes with alternator by Larryish · · Score: 2, Insightful

      New UPS batteries and redundant backup generators sounds like the way to go. Even if your UPS only gives you 2 minutes, that should be enough time to fire up a generator.

    3. Re:stationary bikes with alternator by Anonymous Coward · · Score: 2, Interesting

      I second this. Get small consumer sized UPS units that can keep a server up for a few minutes. Then get a backup generator with an automatic transfer switch to keep the whole building alive until power returns.

      When sizing your generator, don't forget to include ancillary equipment such as routers and emergency lighting if you decide not to wire up the generator for the entire building. Otherwise, sizing should be easy. Just watch your watt-hour meter during a normal business day and add 25% or so to that as a safety margin. That will be the capacity you're looking for.

      Before you go contacting a vendor who will undoubtedly quote you an absurd price, do some legwork and look at the used market for diesel backup generators. The market right now is pretty good for them. Once you have the generator, you can price out the UPS's you'll need and the transfer switch(if the generator doesn't come with one). The cost to have an electrician wire it up should be pretty reasonable given it's a relatively quick job.

      The initial cost to this type of setup is likely higher than equivalent battery based UPS units, but over the long term is significantly cheaper than any large UPS setup.

    4. Re:stationary bikes with alternator by Ihmhi · · Score: 2, Informative

      DirecNIC (an ISP located in New Oreleans) managed to keep their operations going for the entire duration of the Hurricane Katrina disaster and long after that with practically no downtime thanks to their backup generators. They didn't just shut things down - they kept right on going. If you're in an area where power loss or some other sort of disaster is a real threat then this is absolutely the way to go. Bonus, you can pretty much keep the UPSes you have because they just need to keep the systems online long enough for the generators to switch on (as the parent said).

    5. Re:stationary bikes with alternator by Hognoxious · · Score: 2, Interesting

      When you try to start the the diesel engine, it usually having a compression ratio of 12 to 1 or greater, since liquids don't compress, the engine tends to come apart in various manners (bent or broken rods if you are lucky).

      Diesel is a liquid too, so why doesn't it break all the time?

      We'll leave aside the fact that what gets compressed prior to injection of the fuel and the power stroke is air, which is compressible.

      The fact is that the water is denser and sinks to the bottom, which is where where the pipe is - and you can't run a diesel engine on water. Most diesels have a trap or U-bend to catch the water, which you need to bleed off from time to time.

      --
      Confucius say, "Find worm in apple - bad. Find half a worm - worse."
    6. Re:stationary bikes with alternator by Muad'Dave · · Score: 2, Interesting

      Be careful sizing a backup generator when a large part of its load will be switching supplies and UPSes. UPSes in particular have _very_ strange load waveforms due to the rectifiers that are used in the charging circuit. The harmonics passed back on the line can cause the generator to 'seek' trying to lock in to 50/60 Hz, which can cause significant damage.

      A permanent magnet generator can help, but they're a little more expensive.

      http://ecmweb.com/news/electric_ensuring_generator_ups/

      http://www.physicsforums.com/archive/index.php/t-186969.html

      --
      Tiller's Rule: Never use a word in written form that you've only heard and never read. You will end up looking foolish.
  2. Have you tested the UPS lately? by plopez · · Score: 5, Insightful

    This is sort of off topic, but when was the last time you tested the UPS units that were installed "some time ago". The batteries can eventually go flat. You better check what you have ASAP. You may need to replace them sooner than you think.

    I can't remember the brand, but some of the higher end UPS units I have used came with monitoring software. They software polled the UPS unit, and started the shutdown as soon as a power failure caused the switch over to battery.

    HTH.

    --
    putting the 'B' in LGBTQ+
    1. Re:Have you tested the UPS lately? by Lehk228 · · Score: 2, Insightful

      Even a cheap $30 APC backup has a USB connector and windows recognizes it automatically and can start a shutdown / hibernate immediately when power goes out

      --
      Snowden and Manning are heroes.
    2. Re:Have you tested the UPS lately? by TheLink · · Score: 3, Insightful

      The trouble with most UPS battery tests is they involve putting the stuff on battery...

      If you have a server with redundant power supplies- then you can have each power supply attached to a different UPS, then you can test each UPS one by one, hopefully without the server going down due to one UPS failing the battery test.

      You don't necessarily want to shutdown immediately. I have my machine shutdown once the software thinks there's only X seconds of battery life left. Set X to something high enough so that there's enough time to shutdown AND cold boot AND shutdown again... Otherwise in event of a shutdown you will have to wait some hours till the UPS is charged enough before it is safe to power up - in case the power company or whoever cuts power on you half way during your boot up :).

      --
    3. Re:Have you tested the UPS lately? by rs79 · · Score: 3, Informative

      I had a $3000 UPS to keep a big Sun alive. After a couple of years they're $99 on ebay with dead batteries. But they have some of the cleanest pure sine wave power you ever saw. Best. Inverters. Ever. Capish?

      The batteries last 5 years then you replace them, period. They're "Sealed lead acid" or "SLA", in plastic cases with two tabs. They come in various sizes. Get the same ones. Be careful where you get them. $8 batteries off ebay tend to be $40 in the wrong store, for example, one is the same as a chair lift, and the medical devices store that have them in stock want $40 ea. Of course shipping LEAD acid batteries ain't cheap.

      The batteries for the UPC2200, just as an example, are $150 new for the pair plus shipping. $99 for the chassis (plus shipping and they're ungodly heavy without the batteries) and you have a $3000 UPS.

      That'll keep a small server running for a while if you give them one each. But you'd have to be a bit of a dick to have a dozen of these running a dozen servers, what you want is a one ton 12V battery, the kind your phone CO might use, a huge ass inverter and some panic circuit to cut power over to battery when the line goes down. That's the proper way to do it. Once a year they come out and recharge your battery for a small fee. These batteries cost a grand or two but last a long time. Refurbs are fine.

      The other nice thing about big batteries is if you get wind or solar stuff added on the to the
      building you can just wire that power in to the battery with no charge controller. Cause, uh, there's no fear your solar panels are gonna overcharge a ONE TON battery.

      --
      Need Mercedes parts ?
    4. Re:Have you tested the UPS lately? by tagno25 · · Score: 2, Informative

      If it is a Linux (or BSD) box then he can use APCUPSD. It can send emails, has network feature to let other machines know the status of the UPS, and even has a web interface for monitoring the UPS.

    5. Re:Have you tested the UPS lately? by Idarubicin · · Score: 2, Insightful

      The best way to test your power backup system is to throw the main switch and see what fails.

      I'd say that's the most rigorous, realistic way to test, but I'm not sure that it's the best way to test.

      So, you pulled the main breaker and took out all of the production servers because there was a problem with your UPS configuration software? Oops. Why didn't you try it on one server today, then one rack tomorrow, and then pull the plug on the whole system after close on business on Friday?

      Pulling the Big Red Switch is one good way to test, but it's not the only way, and it almost certainly shouldn't be first thing that you try.

      --
      ~Idarubicin
    6. Re:Have you tested the UPS lately? by mrmeval · · Score: 3, Informative

      http://www.apcupsd.com/

      Apcupsd can be used for power mangement and controlling most of APC's UPS models on Unix and Windows machines. Apcupsd works with most of APC's Smart-UPS models as well as most simple signalling models such a Back-UPS, and BackUPS-Office. During a power failure, apcupsd will inform the users about the power failure and that a shutdown may occur. If power is not restored, a system shutdown will follow when the battery is exhausted, a timeout (seconds) expires, or runtime expires based on internal APC calculations determined by power consumption rates. Apcupsd is licensed under the GPL version 2.

      The developers system
      http://matou.sibbald.com/cgi-bin/multimon.cgi

      --
      I'd go on a Vegan diet but the delivery time from Vega is too long. --brownkitty
    7. Re:Have you tested the UPS lately? by Idarubicin · · Score: 2, Insightful

      What if the power goes out on Wednesday?

      That's my point, really. Test in situations where a failure has less severe consequences and you can troubleshoot smaller pieces first. Do the full-on Wednesday-morning test after you can pass the other tests.

      While it's important to be able to recover from a power failure, it's also important that designing and testing your redundant power solution doesn't do more damage to the business than not testing.

      --
      ~Idarubicin
    8. Re:Have you tested the UPS lately? by Blkdeath · · Score: 2, Insightful

      The power going out on Wednesday is why you run your test on Friday--you test your protection to ensure that you can recover from a mid-week power failure by Thursday morning, but you don't run the actual test on Wednesday. You set your test up so that a catastrophic failure causes the least disruption.

      When I was in the Navy, we would run drills in the same manner--our response was the same whether the sub was running deep and fast or slow and shallow, so why run the drills in the riskier situation of deep and fast, where a catastrophic failure in response to the drill could cause very bad problems very quickly?

      But in a data centre you don't face the risk of drowning and/or perishing. Also, it's really easy to convince yourself that your setup works because you've carefully and methodically powered down each backup source individually, but it's near impossible to determine the stress that would be placed on a network by a power failure unless you simulate one. Obviously you have to take steps before hand to make sure your stuff is reliable and you're not going to run a full shutdown while everyone is accessing the data (that, by the way, is a lovely strawman everyone is putting up).

      The fact of the matter is, if you're not confident enough in your data centre's reliability to throw the switch, your data centre just isn't reliable enough.

      --
      BD Phone Home!

      Shameless plug. Like you weren't expecting it.

    9. Re:Have you tested the UPS lately? by Endo13 · · Score: 2, Insightful

      The fact of the matter is, if you're not confident enough in your data centre's reliability to throw the switch, your data centre just isn't reliable enough.

      Well, yeah. That's really the whole point in this discussion - they don't know it's reliable enough. Therefore, throwing the switch on the whole center at this point is foolish at best. You don't do that until you're reasonably confident based on other smaller tests you've done first. Which I believe was exactly what was being stated. Sometimes you have to learn to read between the lines, and understand things without having every little detail explicitly spelled out for you.

      --
      There is no -1 Disagree mod. Slashdot.org/faq defines mod options. USE IT.
  3. Generator by binarylarry · · Score: 4, Informative

    Get a generator that can power things from natural gas (or other available resource).

    So when the power goes out, it will be seconds before the generator kicks on and the UPS are just there to keep power available until the generator is ready.

    --
    Mod me down, my New Earth Global Warmingist friends!
    1. Re:Generator by Joe+The+Dragon · · Score: 2

      For a Generator only 2 min battey time may be cutting it a little to close

    2. Re:Generator by Hadlock · · Score: 2, Interesting

      Out company got to the point of almost bribing building management to let us put a generator on the roof for our use, since the cell companies already had diesel generators up there to power their cell phone antenna equipment. They still wouldn't let us though.

      --
      moox. for a new generation.
    3. Re:Generator by afidel · · Score: 4, Interesting

      Our diesel standby generators kick on and assume load in 20-30 seconds. Of course we have a maintenance contract and weekly generator tests to make sure that stays true, a neglected generator probably won't kick on at all.

      --
      There are 4 boxes to use in the defense of liberty: soap, ballot, jury, ammo. Use in that order. Starting now.
  4. A second site by Colin+Smith · · Score: 2, Insightful

    With redundant connection.

     

    --
    Deleted
    1. Re:A second site by JWSmythe · · Score: 3, Interesting

          There's an awful lot to be said for redundancy. I think he's talking in-house applications, but I'm not positive.

          One company I worked for, we maintained equipment in multiple datacenters, that were fully redundant. Normally, we served from all of them (no warm-standby sites). Over the years, we'd lose datacenters for various reasons. Sometimes it was power. Sometimes it was connectivity. Sometimes it was simple things, like our own hardware died. We've all seen where portions of the Internet can't reach other portions. Such redundancy will save you. It's better to have the reputation of "they just always work", rather than "they're down every time there's a problem in [insert area]".

          Most users won't say "thank you", but they'll be more than happy to complain when you're down. If you have such a presence, you're probably making money on it, so an hour of downtime can easily cost more than the cost of a couple redundant datacenters. With say 3 datacenters, I always made sure we had capacity at each datacenter, in case we had two sites fail simultaneously. While it seems like an almost unheard of event, we did have it happen a couple times in a decade. The providers will apologize profusely, but that doesn't make up for the money lost during the outage.

      --
      Serious? Seriousness is well above my pay grade.
  5. First, know the load! by Nuitari+The+Wiz · · Score: 3, Informative

    Not knowing the load required on the UPS makes it very hard to tell what kind of UPS you need. You need to know how many watts are used in the rack to be able to plan some proper UPS capacity.

    apcupsd can be networked between machines and can trigger auto shutdowns of all of them, including VM guests.

    Some virtual machine system can also suspend all VMs on shutdown which could be a better alternative then shutting them down. Again, without knowing which VM system you use it's hard to get into details.

  6. 1st. Identify Requirements by narziss · · Score: 5, Insightful

    It's not about the amount of people, servers, or a fixed time limit to preserve power. First and foremost, you need to identify what the critical systems are that need to be protected. These may include the VM farms, NAS storage, obviously the underlying network infrastructure, and at the very least, some management terminals that can be used in the event of a failure. Once you identify these systems you need to reference the electrical in/output specifications. If possible, you would want to measure the real requirements in production with inline monitors or passive taps. After you have built your requirement set (mind you, you may decide it's better to have a few small UPS vs one very very large one) you need to explore what needs to be up, and for how long, and build yourself a model. There are dozens of UPS manufacturers, and tens of thousands of combinations for any sized company. Once you have an outline of the systems and their individual power requirements, coupled with your own requirements for their availability/protected power, it will be relatively easy to build yourself a good level of protection on a small budget. Mind you these devices (UPS) can often be found on the second hand market due to company refresh, datacenter closures, etc. Many can be easily re-certified by the manufacturer directly or a variety of 3rd party vendors who specialize in this type of infrastructure.

  7. Diesel by mangu · · Score: 4, Insightful

    No matter how much battery capacity you have, it will eventually run out. If your site truly needs availability, you have to get a diesel generator.

    1. Re:Diesel by Colin+Smith · · Score: 4, Insightful

      If your site truly needs availability, you have to get a diesel generator.

      lol.

      If your site truly needs availability, you need a second site.

       

      --
      Deleted
    2. Re:Diesel by mangu · · Score: 3, Insightful

      Protection against backhoes is a redundant path, not a redundant site.

  8. More Infromation Needed by Anonymous Coward · · Score: 2, Informative

    You haven't provided enough information. To answer your questions we'd need to know how many racks, how many watts or Vamps per rack, or even the type of servers you're running. On top of that you mention that cost is an issue, but you don't mention a budget.

    Without having that info imagine the following scenarios:
    1. You have 1-2 racks with 4-5 piece's of equipment each
        Get a Large APC (or comparible unit for each rack)

    2. You have 1-2 racks halfway populated
        Get an expandable hardwired rackmounted APC

    3. You have 1-2 (or more) racks fully populated
        Get a large hardwired dedicated UPS

    Of course none of this considers anything beyond just bringing the systems down gracefully. If you want something more than that you might want to consider an outsourced datacenter or a generator.

  9. Network UPS Tools by Yonatanz · · Score: 2, Interesting

    The open source world has NUT to offer (Network UPS Tools).

    We've been using it at work for all our critical servers. It works with pretty much all UPSes, and on pretty much any production OS, so you can use your existing servers and just buy whatever hardware the budget affords.

    The linux/unix servers and clients are excellent, and there is a reasonable Windows port for the client (which we've modified a little to suit our needs).

    The cost is just your sysadmin's time, as with all F/OSS solutions.

  10. HP by Thnurg · · Score: 3, Informative

    We have had good experiences with the HP R5500 XR. You may require a smaller and cheaper model like the R3000 or R1500 depending on your servers.
    These UPS are fully supported by NUT.

    --
    The months are just too short. I can count the number of days on one hand.
  11. APC SmartUPS by ircmaxell · · Score: 4, Informative

    I have 2 3000 watt APC SmartUPSes per rack. They have both Serial and USB notification. Since each rack has about 25 servers, I get around 25 to 40 minutes of runtime for each server. So I have a small PC for each rack that monitors those 2 devices. It connects by serial to the upses, and runs CentOS. Then I have APCUPSD installed and configured in multi-ups mode. On each server, I simply install APCUPSD (There is a windows version), and tell it which UPS it is on. I also configure the appropriate shutdown parameters (20 minutes of battery left for non-critical servers, 15 for DC, and 5 for other critical servers. I also hooked each UPS monitor into Nagios and Munin, so I can track each one's power output and time remaining. So far, it's worked great over 2 "brownouts", and 1 total power failure (a test where I simply tripped the appropriate breakers).

    The rational behind having dedicated UPS monitors, is that I don't really care if the loose power while running, so I have them set to never shut down from UPS activity. Then, I simply implemented a script that on power restore issues a netboot command to each server under its control (configured with puppet for Linux, AD for Windows). That way, the whole system (all servers) automatically shut down, and turn themselves back on even if they never really lost power... So far, it's worked flawlessly (and with nagios, I get a text message on my cellphone within a minute or two of a UPS switching to battery (we have 2 dedicated internet connections that are on different power sources and different UPSs.

    I hope this helps!

    --
    If a man isn't willing to take some risk for his opinions, either his opinions are no good or he's no good
  12. Break out the calculator and spreadsheet by darkjedi521 · · Score: 3, Informative

    Its time to break out the calculators and do some math. There are two main factors at work here, UPS load capacity and battery run time. I run a series of research clusters at a university, so only the core systems (landing pads, schedulers, auth, disk arrays) are on UPS and all the compute nodes just die at a power hit.

    Retrofitting a datacenter for whole center UPS is a very daunting and expensive task, so odds are good you'll be replacing the current rack mounts with beefier units, either pedestal sized units next to their racks or rack mounted units.

    When buying UPS gear for work, I aim to hit either 67% capacity with the planned load, or the smallest VA rating that takes 208V single phase, as long as its at least 1/3 under utilized for future expansion. That covers the VA rating. As for battery run time, most of the larger units accept external battery packs to increase the run time. I've never used them, since a 5KVA unit with my load gives me 20 minutes of run time, and if the power isn't back on by then, odds are good its not coming back any time soon.

    Another option for extending UPS run time is to prioritize services/VMs. With the appropriate monitoring software on each host, you can configure each host to shutdown when the UPS estimates X minutes of battery time remaining or there have been Y minutes on battery, or both. Less load, more run time for the really important stuff. Almost every UPS I've used (APC, Tripp-lite, Powerware) comes with off the shelf software or there are opensource solutions (apcupsd, nut) for monitoring the UPS over serial, USB, or SNMP (Options vary with mfg and model). My shutdown schedule is: after 5 minutes on battery, power down the compute cluster landing pads. With 10 minutes remaining, power down the file servers with the archival data on them. With 6 minutes remaining, power down the primary file servers. With 2 minutes remaining, power down the auth box/network monitor/iLom control host (This is the only one that can't get powered on/monitored remotely).

  13. Inverters by mukund · · Score: 4, Informative

    I use a Su-Kam inverter at home. It powers a whole room, has a clean sine-wave output (unlike traditional UPSes), and its switchover delay is small enough that the SMPS in computers handle the switchover to battery power properly.

    It uses two large lead-acid multi-cell batteries (~car batteries) for storing charge. The last time there was a major power cut, it powered my computer systems for 10 hours (yes you read that right... 10 hours.)

    I was laughing at the old APC UPS which did 10 minutes before I had to power down.

    This is India btw.. power cuts are common.

    --
    Banu
    1. Re:Inverters by mukund · · Score: 4, Informative

      Oh and I forgot to add.. the whole setup cost me ~$600 including installation. Maintenance costs about $1 / month (topping up distilled water levels). Also the 10 hour duration I quoted above was the duration before mains power came back on. I suppose it would work for quite a bit longer, but the power hasn't been out for a longer duration. Also, this is a "home" sized product. You can get larger solutions if you want longer backup. Many companies use such solutions in India to beat the power cuts.

      --
      Banu
    2. Re:Inverters by mukund · · Score: 2, Interesting

      Photos are in another comment in this thread. The model I have is a Smiley 1400VA / 24V. I don't know if you'll find this in your country, but you should be able to find some local good-quality brand like it. Best is to contact a local dealer and ask them. Batteries are made by Exide. I don't remember the model number, but your local shop should be able to suggest good ones for you, that meet your requirement. I called up a local dealer here with my requirement ("I want to power X computers with the following components for N hours"), instead of doing the math myself.

      --
      Banu
  14. Larger UPS by JWSmythe · · Score: 2, Interesting

        It sounds like you may have outgrown the traditional "UPS". They're fine and dandy as long as you're only powering so much equipment. There are some huge options (large in physical size, and more so in price).

        A decent alternative may be a DC power room, with generator backup.

        Basically, you have banks of batteries, with true sine wave power inverters on them. The power coming in goes to charge controllers. Depending on how you set up, these can get pricey too. There are some nice (and expensive) units that handle both the charge controlling and inverting, and will automatically switch between the incoming power and batteries. Look at the higher end Xantrex units, made for on/off grid purposes.

        The less expensive way would be to break up your battery banks by power circuit. Say a 15A power circuit per set. Put a dependable inverter on the rack side of the batteries, and a good charge controller on the line side. Separate inverters for each circuit may not seem like the best idea, and the overall efficiency will hurt because of it, but an inverter failure will only mean one circuit goes down, not the whole place. It's affordable to keep a few spare $300 inverters on hand, where it's harder to ask for a few spare $3,000 inverters.

        You'll also want an automatic crossover, if your line power should fail, you can bring up a generator. The batteries shouldn't be intended to last for hours. They should only last as long as it takes to bring up the generator (say 1 minute). Expect that there may be generator problems though. In a prolonged outage, you may need to shut down the generator to refuel, so the batteries may need to last for hours. At very least, if your generator fails, and line power doesn't come back up, you have that hour to gracefully shut down your equipment.

        Such a setup can be made to make your company more "green" too. Are you in a situation where you could put a large array of solar panels on the roof, and have enough battery power to last you through the night and then some? You could bring your power bill down to almost nil, or possibly feed back to the power grid (with the appropriate permission and power meter), and make a little money in the process. The long term savings may warrant a raise for you. :)

        There are plenty of consultants that can evaluate your needs, and provide the appropriate solutions. As you talk to various consultants, several will say the others are giving you bad advice. Look at all of them, and research them for yourself before making a decision. Remember too, it's in *their* best interest to sell you the most expensive units possible, while you probably want the most reliable and cost effective.

    --
    Serious? Seriousness is well above my pay grade.
  15. Cost of UPS vs Colo? by Hadlock · · Score: 2, Insightful

    What's the cost of a good set of UPSes vs simply migrating to a Colo & fatter pipes? Datacenters (most of them anyways) promise at least a few hours of generator uptime, and it sounds like you're already using a colo somewhere (dns relocation, etc).

    --
    moox. for a new generation.
    1. Re:Cost of UPS vs Colo? by JWSmythe · · Score: 4, Interesting

          I think he was talking about in-house servers, but I could be mistaken. it's good to be in a *GOOD* datacenter that has the proper redundancy. Most of the good ones have multiple generators and tens of thousands of gallons of fuel stored. They can stay running indefinitely, assuming they can get fuel supplied before they ran out.

          I did work in one good one. They had a DC powerplant to supply at least 24 hours of power. They also had two diesel turbine generators, and something like 10,000 gallons of fuel, which would provide power for 7 days. In talking to the senior techs who had been there an awful long time, they said the generators had kicked on quite a few times. Only once in about 20 years had they needed to refuel. It got touchy. The power was out for about 14 days. It took 6 days to get a refueling truck in, because it was a nasty blizzard, and all the roads had been closed for days. They were starting to notify the customers of a potential power outage, when two fuel trucks finally arrived. One refilled their tank, and the second was left parked there, in case power wasn't restored in time.

          That was a huge facility, and they had the power to say "bring us trucks now", and not be put off for larger customers.

          I wasn't impressed by the advertised specs of the site. They were good, but it's easy to lie about the specs. I *was* impressed by the site, when I walked through, and was allowed (with an escort) to see their primary data room (many OC192's), the DC power room, and generators. I wasn't getting the sales tour. I was getting the tech tour, because the senior guys wanted to tell me all about their stuff, and we had a chance to talk about all of it.

          I've been to many datacenters over the years, and many have failed to be as good as their advertising made them sound. N+1 generators can be a few 11Kw generators out by their dumpsters, or massive industrial generators. Maybe they test them once a year, or once a week. Maybe they work, maybe they don't. It's less than impressive to see the generators sitting outside, covered in rust, and looking like they were purchased 2nd hand and hadn't been maintained since 1950.

          At one site (again, an impressive site), they had an absolutely huge DC room, and I was there a couple times when the received phone calls to turn on their generators because the power company needed the extra capacity. A couple 1Mw generators may make the difference between constant power, and widespread brownouts.

          The impressive datacenters were way beyond anything I could possibly talk my management into doing in-house.

      --
      Serious? Seriousness is well above my pay grade.
  16. Re:30 people by lukas84 · · Score: 2, Informative

    Meh, a 5500 VA UPS can drive a rack full of low-end 2U servers.

  17. Leave it to the professionals by chill · · Score: 4, Insightful

    Co-locate your equipment at a carrier-grade data center in the nearest major city to your location and get a leased line to your premises. A decent data center will have proper battery backup and generators and know how to handle it. They'll also have the time and manpower to do proper tests, etc.

    --
    Learning HOW to think is more important than learning WHAT to think.
  18. Re:1st. Identify Requirements by JWSmythe · · Score: 4, Insightful

    It's not about the amount of people, servers, or a fixed time limit to preserve power.

        You're absolutely right. One place I worked had about 20 employees, 150 servers, but had an income of millions per year. The income averaged out to about $5,700/hr. 12 hours of outages per year could cost almost $70,000 in lost revenue. Is it worth $10k in extra equipment to mitigate that? Obviously.

        Smaller companies have to evaluate their acceptable losses. Sometimes it's not worth $100 to make sure you stay up through power outages.

      "5 9's" of reliability still leaves 1.14 hours per year of outages. Of course, that doesn't assume that it's all power related outages. Redundancy across physically diverse locations can and will help there.

    --
    Serious? Seriousness is well above my pay grade.
  19. Re:Shill detected by mukund · · Score: 4, Informative

    It's no act. I am happy to put up photographs of my setup if you want. It's been working well for me the last year, so I don't have issues recommending it. Apart from being a customer, I have no connections to any inverter/battery company. You OTOH are an anonymous coward. Here is my website. Go find more about the shill there.

    --
    Banu
  20. Eaton is excellent by wysiwig3 · · Score: 2, Interesting

    I moved away from monster APC & Leibert units a bit over a year ago, and I'm so glad. I encourage you to look at the Powerware BladeUPS units. Each provides 12kW capacity, with internal batteries and the ability to string two additional external battery modules (EBMs) for increased time. In addition, the unit is stackable up to 6 high in a cabinet yielding 60kW (in an N+1) configuration. You can grow it as you need it. Nice Web/SNMP card that can be added for all the info you could want. With the N+1 config, you can shut down any single unit for removal, repair, or battery swaps. These things are so much less hassle than my old equipment that I won't be looking elsewhere for a while.

  21. Propane Explosions by Cassini2 · · Score: 2, Informative

    Not properly maintained propane storage/transfer sites have be known to explode. For instance: the 2008 Toronto explosions, the 2006 explosion, and the Feyzin disaster. Propane is highly vulnerable to a BLEVE - Boiling Liquid Expanding Vapour Explosion. Many more smaller propane exposions have occured, they just did not make the news.

    I've seen what happens when Propane explodes. I would think twice about using it for an emergency backup fuel source.

  22. Re:1st. Identify Requirements by trum4n · · Score: 2, Funny

    You run Windows Vista on your servers?

  23. Re:Shill detected by couchslug · · Score: 2, Informative

    "I can smell the curry from here."

    Shmuck detected.

    Large lead-acid batteries (or Optima batteries if servicing is a concern) are cheap compared to most UPS batteries, inverters are old, proven technology, and systems using them are easy to set up.

    --
    "This post is an artistic work of fiction and falsehood. Only a fool would take anything posted here as fact."
  24. Colocation by liam193 · · Score: 2, Interesting

    With the current availability of fairly inexpensive bandwidth, why are you running servers at your location? There simply isn't much justification for any business not in the fortune 500 to go the route of "build your own" Catacenter. If it must be up, look at the option of renting rack space from a Telecom provider that takes care of generator power for you. Most of these will do a rack for a couple hundred a month that includes the generator backup. You may need to get a small UPS that handles the "blip" until the generator kicks in (they usually tell you that you need a few seconds of UPS), but it sounds like you already have units to put at the bottom of the rack that will handle that. You then have servers that will survive as long as the provider has fuel. Anything else is going to cost you far more. Most likely you can find one that will provide decent bandwidth from your location to theirs and provide you with an Internet connection at the Colo that is less expensive because it doesn't have the local loop to your facility. This probably would offset much of the cost for bandwidth that you will need from your office to your servers at the Colo.

  25. Redundant PSU vs. UPS by Hymer · · Score: 2, Informative

    An UPS is not an alternative to redundant PSUs, it just seems that way until your PSU fails.
    I've got a server room with about 150 servers (physical and virtual) every physical server got redundant PSU and the whole room runs on a PowerWare 9305 30 kVA UPS.
    ...and yes I should have redundant UPSes too, I just dont have the room for another one.

  26. 1 UPS per PC by AliasMarlowe · · Score: 2, Informative

    At home, I use 1 APC UPS per PC, except for the laptop. These cheap units give about 30 minutes for the PC and its immediate peripherals (displays, external disks). The PCs run Ubuntu, and automatically recognized the UPS units when they were connected via USB ports. Another UPS powers the fiber switch, headless server, and router. Yet another keeps the network printer and an ethernet switch powered. Total of 4 APC UPS units and less than 350euro investment.

    We need this, because we're in the countryside, where power glitches are depressingly common - but often last just a second or two. If the outage lasts until the UPS goes below 50%, then the systems shut down gracefully. By then, of course we would have saved any work in progress. Keeping the whole LAN in operation during this time is essential.

    --
    Those who can make you believe absurdities can make you commit atrocities. - Voltaire
  27. Re:Shill detected by mukund · · Score: 3, Informative

    Here they are: inverter1.jpg, inverter2.jpg

    I'm sorry it's pretty dusty, but this has been exposed to the elements for the past year. It has to be kept outside because of the lead-acid batteries, which need to be ventilated. The stand is an old TV stand reused to host this. The inverter is on top. The batteries are at the bottom.

    The little yellow alien looking caps that you see filters that the acidic fumes from the batteries. Each cap tops a cell. The little stick on top indicates the liquid level inside the cell. After about a month, the levels go down in some of the caps and I call the local shop to come and top-up distilled water. Basically the water evaporates whereas the acid is still there, so they fill in distilled water. I could do this myself, but the local shop does it for about $1 so I just let the experts handle it :).

    --
    Banu