Gulf Oil Leak Plugged?
RobHart writes "The LA Times is reporting that the Gulf oil leak appears to have been plugged by the 'top kill.' 'Thad Allen, who is coordinating the government response, says the well still has low pressure, but cement will be used to cap the well permanently as soon as the pressure hits zero.'"
This is just step one of the top kill. It's just plugged with mud, which is still streaming out of the hole. Don't start celebrating until they actually top it with concrete.
I've got to wonder, if this does work is BP going to go ahead with their "relief well".
Give me Classic Slashdot or give me death!
They had to fabricate all kinds of gear that had never been made before. This was a herculean effort by 100's of the most skilled deepwater engineers in the world, and they actually did it in record time. This was not a small task, it would normally take months to pull something like this off.
I'm looking forward to seeing BP get raked over the coals. Bastards. The way they attempted to cover up how bad the spill is is really disgusting. See http://www.newsweek.com/2010/05/26/the-missing-oil-spill-photos.html
latest "live" thread with great insights in the comments: http://www.theoildrum.com/node/6515
Relevant links to top kill procedure (scroll to comments in each, they're very good.)
Deepwater Oil Spill - Permissions and Concerns about Top Kill http://www.theoildrum.com/node/6513
Deep Water Spill - Waiting for Top Kill (more updated tech) http://www.theoildrum.com/node/6509
The Gulf Deepwater Oil Spill - the Top Kill Attempt (the technical aspect of what just happened) http://www.theoildrum.com/node/6505
The Gulf Deepwater Oil Spill, barriers, flow rates, and top kill http://www.theoildrum.com/node/6501
Hope you find this informative...
Though the name's confusing, a "relief well" isn't a separate well into the original reservoir that can be put into production. It's a well that's drilled at at an angle, calculated to intercept the bore of the original well somewhere in the rock above the reservoir. If it intercepts it, pressure gets diverted up through the new well, which is presumably under control, and then a bunch of heavy mud is pumped in to plug it up.
10 PRINT CHR$(205.5+RND(1)); : GOTO 10
I was told by one of my old girlfriends who works for Schlumberger (she has her own sources) that this isn't a permanent fix. They are doing a top fill because it is faster than waiting for the relief well to do a bottom fill. This top fill is likely a temporary measure, and they are still going to have to drill a relief well to intercept the main well which is going to take time.
We can only pray that once they cap this, it sticks till they can get the relief well fully drilled.
Before you accuse other people of ignorance it might help to do a little research. By many estimates this spill is much larger than the Exxon Valdez spill. See for example http://news.yahoo.com/s/nm/20100527/us_nm/us_oil_rig_flowrate.
The relief well does not divert the pressure. They can use it to inject mud (which has a density much higher than oil or seawater) into the original bore. As the mud fills the well, the higher density will increase the pressure until it matches the outward pressure of the reservoir.
So 8,000 vertical feet of seawater/oil is not enough to stop the leak, but 8,000 vertical feet of drilling mud that has a much higher density can do the job.
Nerd rage is the funniest rage.
You are describing the containment dome, which was tried and failed.
It failed because of the high pressure and low temperature. Methane from the well was forming Methane Clathrates, which would plug up the hole.
The "Top hat" fix was going to use a dome into which they pumped hot methanol to keep the pipe clear, but it seemed less likely to work than the current approach.