Chevron Got North Sea Contract Despite IT Safety Crashes
DMandPenfold writes "The UK government gave Chevron the go-ahead in September to drill in the North Sea off the coast of Scotland, in spite of the US oil giant's admission that its contractor's spill prediction software constantly crashed and was not a reliable predictor of how far oil could travel if an accident took place. The news comes in a week that US investigations into BP's disastrous Deepwater Horizon oil spill hit the buffers, after an IT contractor firm refused to hand over access to its software."
http://en.wikipedia.org/wiki/Piper_Alpha
"An explosion and resulting fire destroyed it on July 6, 1988, killing 167 men, with only 59 survivors. The death toll includes two crewmen of a rescue vessel. Total insured loss was about £1.7 billion (US$ 3.4 billion). At the time of the disaster the platform accounted for approximately ten percent of North Sea oil and gas production, and was the worst offshore oil disaster in terms of lives lost and industry impact."
"People were still getting off the platform several hours after the initial fires and explosions. The main problem was that most of the personnel who had the authority to order evacuation had been killed when the first explosion destroyed the control room. This was a consequence of the platform design, including the absence of blast walls. Another contributing factor was that the nearby connected platforms Tartan and Claymore continued to pump gas and oil to Piper Alpha until its pipeline ruptured in the heat in the second explosion. Their operations crews did not believe they had authority to shut off production, even though they could see that Piper Alpha was burning."
Why is Snark Required?