Spreadsheet Blamed For UK Rail Bid Fiasco
First time accepted submitter Bruce66423 writes "As a sometime computer programmer who was always very sniffy about the quality of the stuff being knocked up by amateurs aka power users, the current claim that it was a messed up spreadsheet that caused a multi-million pound fiasco is very satisfying. 'The key mechanism... mixed up real and inflated financial figures and contained elements of double counting.'"
Spreadsheets -- well, Excel really -- are inescapable in business.
I know personally of complex multimillion dollar deals in the oil and gas business involving buying and selling entire refineries and gas pipelines where the numbers were all worked out on a spreadsheet.
The insurance industry lives on the spreadsheets put together by the actuaries.
The only consistent reason I've seen for Excel users will give up their rows and columns and have bespoke software created is when the dataset gets cumbersomely large. A secondary reason is when the kinds of calculations needed can't be cobbled together with Excel's function and macro tools. Even then, it's not unheard of for users to demand summary/aggregate reports and analytics that they then copy the numbers from into their spreadsheet to do their scenarios.
Just keep in mind the next time you hear about big money moving around in some deal -- somewhere someone probably had a pivot table for that.
The way our railways were privitised (which has been a total disaster btw), is that the government leases out monopolies on routes to companies for 10-15 years. This is about one of the routes coming up for renewal and the contract being taken away from the current operator (Virgin). After the announcement of the winner, Virgin said the other company had made an unrealistic bid and wouldn't be able to operate the route at the quoted rate. Now it turns out the government department overseeing the bidding process has messed up the calculations when assessing the feasibility of the bid.