Ask Slashdot: Development Requirements Change But Deadlines Do Not?

cyclomedia writes "Over a number of years my company has managed to slowly shift from a free-for-all (pick a developer at random and get them to do what you want) to something resembling Agile development with weekly builds. But we still have to deal with constant incoming feature changes and requests that are expected to be included in this week's package. The upshot is that builds are usually late, not properly tested and developers get the flak when things go wrong. I suspect the answer is political, but how do we make things better? One idea I had was that every time a new request comes in — no matter how small — the build gets pushed back by 24 or even 48 hours. I'd love to hear your ideas or success stories. (Unfortunately, quitting is not an option)"

2 of 221 comments (clear)

  1. You've already lost this battle by Mandatory+Default · · Score: 5, Informative

    You think you're fighting manager's lack of understanding of software development. You are wrong.

    You are fighting politically savvy people who have found a way to blame you for their problems. They don't want you to solve the problem and will actively work to prevent you from solving the problem, because then you can't be the scapegoat.

    If you don't have a VP or C-level manager who will fight this fight for you, then you've already lost. Don't bang your head against the wall. Play the same game as everyone else and find someone else that you can use as a scapegoat. Meanwhile, start looking for a new job.

    Even if you miraculously "fix" this problem, someone else is going to claim credit and you're going to get nothing.

  2. Re:Agile is about commitment, not flexibility by rwa2 · · Score: 5, Informative

    "Agile" is something of a misnomer... it's about committing to the work items you've estimated into your current sprint -- and no more. If someone wants to add a feature or request, it goes straight into the backlog for consideration during the next sprint planning session.

    "Agile" is more about setting up a consistent delivery schedule... the build train leaves the same time each week, carrying whatever passed QA testing... and no more. The build train is never delayed, only derailed by an Act of God. That's right, if some exec really thinks that something is so important that it needs to be done *right now*, you completely stop all work, scrap the current sprint and start a new sprint planning session with all of the overhead that entails.

    Anyone who practices differently is not practicing Agile according to the way it was intended. There are no "sprint schedule extensions" in Agile, since it's a measurement and estimation tool... the same way you don't measure with a longer "yardstick" when something is too big to fit in a 1-yard container.