Chinese Company '3D-Prints' 10 Buildings In One Day
Lucas123 writes: A company in China has used additive manufacturing to print 10 single-room buildings out of recycled construction materials in under a day as offices for a Shanghai industrial park. The cost: about $5,000 each. The company, Suzhou-based Yingchuang New Materials, used four massive 3D printers supplied by the WinSun Decoration Design Engineering Co. Each printer is 20 feet tall, 33 feet wide and 132 feet long. Like their desktop counterparts, the construction-grade 3D printers use fused deposition modeling (FDM), where instead of thermoplastics layer after layer of cement is deposited atop one another. The cement contains hardeners that make each layer firm enough for the next. Yingchuang's technique builds structures off site in a factory one wall at a time. The structures are then assembled onsite. The technique is unlike U.S.-based Contour Crafting, a company whose 3D printing technology to form the entire outer structure of buildings at once, The Yingchuang factory and research center, a 33,000 square foot building, was also constructed using the 3D printing manufacturing technique. It only took one month to construct.
Do we know how safe it is to work or live in a building made of these chemicals?
I remember when portables started being added to schools, it was determined all the various chemicals in them were making kids and teachers sick.
They need to determine the potential effects on health first.
They can't be any worse than the corrupt politicians we have in power now.
Those structures are bigger and sturdier than a tiny house with the added advantage of being made from recycled building materials.
The real question is structural strength and integrity and what agents are they using to make the mix dry fast. The Chinese could be using some nasty chemicals that wouldn't fly in building materials over here (Chinese drywall anyone?).
Still, if the units end up being even roughly equivalent to poured concrete, I could see living in a printed house, no problem.
That's our life, the big wheel of shit. - The Fat Man, Blue Tango Salvage
that one caught on fire, burned down, fell over then sank into the swamp
the preceding comment is my own and in no way reflects the opinion of the Joint Chiefs of Staff
Actually, I'm pretty sure I can't.
From the article : "The machines can also automatically embed all the conduits for electrical, plumbing and air-conditioning, as well as place electronic sensors to monitor the building's temperature and health over time."
But not this method of printing half walls in a factory which are then assembled on-site, I'm not sure what they're gaining by doing it this way.
I assume you missed the part about building 10 single-room buildings in a day for $5,000 each.
"Our two-party system is like a bowl of shit looking at itself in a mirror." - Lewis Black
While 3d printing is cool and all what advantage does 'printing' concrete slabs offer or normal precast molds and just pouring the concrete in the old fashion way?
The article doesn't make it clear, but since this is a company and not an experiment one has to assume they see sort of useful reason in doing it this way, but for the life of me I don't see what it is.
If you're using a mold for concrete it's almost literally as fast as you can pour the concrete when using one...
Technology, the cause of and solution to all of life's problems.
RE: the headline
No. From TFA:
Yingchuang New Materials Inc. was able to print the shells of 10 one-room structures in 24 hours
The way this summary is worded, they make it sound like this company actually printed the buildings in place. Which did not, in fact, happen.
An enigma, wrapped in a riddle, shrouded in bacon and cheese
I still don't get how it's supposed to be more efficient than setting up prefabricated moulds, hanging the conduits and placing the rebar, then pouring concrete from trucks... Yes, the moulds have to be taken off after waiting for the walls to cure enough to support themselves, but typically mass-construction of even identical buildings will see staggered stages including rough ground prep, survey for foundation positioning and marking that, installing the in-ground utilities/services/piping, pouring the foundation and slab, finishing off the stub-ups through the slab, building the load-bearing walls, building the roof, roughing-in the interior wall studs, putting in electrical/plumbing/etc, then finishing the interior walls and exterior of the building.
That process can be staggered across several buildings so that the time to build ten buildings in-tandem isn't a lot worse than if two buildings were built, each start-to-finish before the next. I don't see how using a 3d printer really helps. 3d printers are great for prototyping and small-batch work, but it's almost always more cost effective to build special-purpose to make things in volume if the volume is enough to pay for the machines. 3d printing would work great at home or in a boutique shop, but I don't see it being a major factory process for finished goods.
Do not look into laser with remaining eye.
1) offer strength-to-weight savings (vs. solid slab cement walls)
2) use less material for a given surface area (yeah, this follows #1),
and 3) allow some extra insulation if warranted by the destination environment.
Also it would probably allow different configurations depending on how tall one wanted to stack (thicker lower-flow pieces; thinner upper-floor pieces). And the other point about embedding services cabling & plumbing stands; I could see them using standard interconnects to splice things together as they get assembled. *shrug* Maybe all that is common place today with prefab walls; don't know ianapfba (pre-fab building architect).
My first thought was "Big deal, another kind of prefab building" but the design + deposit is pretty interesting. This gets into some of the same things for machining I've read about where casting and/or subtractive (cnc milling) runs into limitations; additive manufacturing can create nested structure that were just not possible before. *shrug* It is cool to see people doing neat things with cement++.
And maybe - at some point - it would be cost effective for larger & taller structures to print segments on-site (and possibly at elevation for multi-story units). I don't know that they need to print in-situ; having useful-sized freshly printed & cured components (think just-in-time lego-blocks for the construction crew) could still be useful.
(One downside: I wonder about the "quick-set" additives and how nice (or not-so-nice) it would be to breath anything that off-gassed after it was all put together.)
Well you see the whole show was technically an illusion. The extrusion process for the material is really neither here nor there. The computer control of a concrete pump and the outlet of a house. The real important information that everyone is ignoring is the concrete mix. What is in it, how are they achieve higher extrudability with low slump http://en.wikipedia.org/wiki/C..., what is the compressive and tensile strength of the concrete, how is it being reinforced, what are it's insulative properties, how is moisture movement being controlled, what happens when ice forms and how does it handle cracking. Exactly how toxic is the mix and how safe is it to use. What happens when you cut and drill into it.
Everyone loves to focus on 3D printing whilst ignoring the material the is used to do the printing and how it actually performs.
Chaos - everything, everywhere, everywhen