Hitachi Developing Reactor That Burns Nuclear Waste
Zothecula writes The problem with nuclear waste is that it needs to be stored for many thousands of years before it's safe, which is a tricky commitment for even the most stable civilization. To make this situation a bit more manageable, Hitachi, in partnership with MIT, the University of Michigan, and the University of California, Berkeley, is working on new reactor designs that use transuranic nuclear waste for fuel; leaving behind only short-lived radioactive elements.
I don't think they do so in the breeder cycle - their neutron loss margins are fairly thin, hence why most designs propose extracting at the Pu-238 step (unusable for weapons, but great for space batteries). The burner cycle might be better in this regard. Fast reactors are able to do it, they have plenty of neutrons to spare.
Fukushima Daiichi's problems began forty years ago when they removed the natural 35 meter bluff that use to be there.
The plant is on a bluff which was originally 35 meters above sea level. During construction, however, TEPCO lowered the height of the bluff by 25 meters. One reason for lowering the bluff was to allow the base of the reactors to be constructed on solid bedrock in order to mitigate the threat posed by earthquakes. Another reason was the lowered height would keep the running costs of the seawater pumps low. TEPCO's analysis of the tsunami risk when planning the site's construction determined that the lower elevation was safe because the sea wall would provide adequate protection for the maximum tsunami assumed by the design basis. However, the lower site elevation did increase the vulnerability for a tsunami larger than anticipated in design.
Not considered in the above would be the simple yet modestly more costly possibility of obviating the need for a sea wall by preserving the bluff and setting the reactors back, using modestly sized canals to cycle the sea water to and fro. That, naturally, wasn't the cheapest conceivable option, so it didn't survive the bean counters. Instead, they removed 25 meters of foothill, a feature that was originally 2.5 times the height of the tsunami before they fucked it up. The whole `bedrock' smokescreen is easily dismissed for the lie that it is; they could have reached bedrock from a setback design with no more difficulty.
This was done for one reason; grading the beach provided cheaper access to the ultimate heat sink, sea water. Less construction cost, less pumping, less maintenance, etc. This isn't lost on the perpetrators either. They know they're at fault and they knew it at the time, whatever lies they tell today notwithstanding.
This isn't speculation, either. Fukushima Daini did not get submerged, did not melt down and did not contaminate the land and the sea. Why? Primarily because it was built at higher elevation, which is about the only significant difference between these sites.
TEPCO bean counters. End of story.
Maw! Fire up the karma burner!
but it does seem like important stuff in a flood plain
Fukushima wasn't in a flood plain.
Yes it is. Take a look at this US Army topo map (the latitude is (37.427 degrees, its on the coast). It is on an extended flood plain stretching along the coast, created by several rivers (Takase, Maeda, Kuma. Tomioka, etc.) . The whole area is a sea-level marsh consisting of soil deposited by these rivers at flood.
The problem wasn't glaring except in hindsight.
Because, you know, no one had ever seen a tsunami in Japan before. Oh wait, tsunami is a Japanese word. That doesn't seem quite right, does it?
Japan had fifteen of them since 1900, before Tohoku (the slightly dated linked list misses the 2007 Niigata tsunami).
Starships were meant to fly, Hands up and touch the sky - Nicky Minaj