British Airways Says IT Collapse Came After Servers Damaged By Power Problem (reuters.com)
A huge IT failure that stranded 75,000 British Airways passengers followed damage to servers that were overwhelmed when the power returned after an outage, the airline said on Wednesday. From a report: BA is seeking to limit the damage to its reputation and has apologised to customers after hundreds of flights were canceled over a long holiday weekend. The airline provided a few more details of the incident in its latest statement on Wednesday. While there was a power failure at a data center near London's Heathrow airport, the damage was caused by an overwhelming surge once the electricity was restored, it said. "There was a total loss of power at the data center. The power then returned in an uncontrolled way causing physical damage to the IT servers," BA said in a statement. "It was not an IT issue, it was a power issue."
Pretty sure UPS's and backup power supplies kinda do fall under that...
The power surge was the direct cause. The fundamental cause was the failure of management to ensure they had an appropriate disaster recovery plan.
Even if UPS and surge protection do not count, having a redundant system in a different data centre ready to take over regardless of the cause of the outage definitely does fall under IT. It is insane that a major company like BA did not have any such redundancy for such an important, mission critical application. It would have cost far less than the £100 million estimated cost of this incident not to mention avoiding the appalling publicity.
Yep.
We have a Caterpillar generator the size of a schoolbus (and given its coloring I've had to restrain myself from sticking a stop-sign on the side as a prank) and a sophisticated transfer switch with power monitoring. When we lose power the batteries hold the DC over until the generator kicks in, and then when power is restored we do not switch back to grid immediately. I am not the person that deals with the power, but as I understand it, the generator and transfer switch monitors the grid for some time before switching back to grid, and there are power conditioners in between. On top of that, the system monitors grid power continuously and will intentionally island the system if there's a significant enough fault.
This is not for something as critical as an airline's control system either. I do not find any reasonable excuse to blame power; you're supposed to assume that power is dirty and unreliable and to work around it.
Do not look into laser with remaining eye.
This is what happens when you treat your IT staff like your Janitorial staff.
When Fascism comes to America, it will call itself Anti-Fascism, and tell you to give up your guns.