Is it cheaper? Correct me if I miscalculated but... This says that facility has 129 MW-h storage and cost between 50 an 200 million: https://greycellsenergy.com/ex... The US produced 4,015 Billion kWh in 2017: https://www.eia.gov/tools/faqs... Divide by 365 and get 11 Billion kW-h (for just 24 hours backup) or 11 Million MW-h 11,000,000 / 129 is about 85000 85000 * 50 million = 4,263,000,000,000 So 4.3 trillion dollars in batteries
Is it cheaper? Correct me if I miscalculated but...
This says that facility has 129 MW-h storage and cost between 50 an 200 million:
https://greycellsenergy.com/ex...
The US produced 4,015 Billion kWh in 2017:
https://www.eia.gov/tools/faqs...
Divide by 365 and get 11 Billion kW-h (for just 24 hours backup) or 11 Million MW-h
11,000,000 / 129 is about 85000
85000 * 50 million = 4,263,000,000,000