asc4 asks: "The company I work for is a webhosting and colocation company. As our power utilization grows, we have begun searching for ways to make our datacenter more efficient. The biggest hit from the utility company comes in the peak usage charge, which penalizes (rather severely) for the highest sustained burst of usage during a billing period. Due to the nature of the colocation business, we can't control how much or when client devices use power, so I'm wondering: is there's something we can do at the datacenter level to help smooth out our power consumption, over the course of a given period of time?" "In these days of hybrid cars, Energy Star devices, and in general more eco-friendly power consumption, it seems like there must be some products out there that can help make datacenters more efficient, as well. Could fuel cell technology be something to look into? Would flywheels or capacitors help? How about using more efficient AC units than what are available from the big names? What are others doing to reduce peak power consumption in high-drain datacenter environments?"

3 of 138 comments (clear)

  1. How about looking for energy efficient devices... by spagetti_code · · Score: 4, Insightful
    How many of your servers are running at 100% CPU? How about moving them to VIA low power processors - up to 1.3GHz.

    I have one of these (1.2GHz) and with 1 large HDD, encoder card, network, DVD etc - it idles at less than 20W and maxes at about 60 (encoding, playback, DVD all going, CPU 100%). Burst power when switched on seems to be about 72. This is less than the processor alone on a high spec box.

    This will only work with non-CPU intensive operations. However IO seems to be pretty good on these boxes, so an IO bound server would probably not suffer too greatly using a VIA mobo.

  2. Hoe much money you got? by RingDev · · Score: 3, Insightful

    Some things are easier to do in the design phase. but something can be done now.

    First, pre-cool the room. There was a good article on /. earlier this week, keeping the building cooler in the morning and warmer in the afternoon can drop your peek time costs.

    Second, install a solar power system. Kinda pricy, but if you have a large roof you can generate some solid power. And don't think that being in the north excludes you from solar power. Uni-Solar has a great sun index map showing what level of solar output and electrical output you can expect in any given area.

    Third, going with solar, a battery array or some other type of power storage. By using the solar pannels to juice up the batteries, you can pull power from the batteries at peek time, but charge them all day.

    Fourth, sub-teranian cooling. Once you get a little ways under the surface of the ground, the temperature becomes a pretty consistant mid/high 50's. Using sunken water tanks you can run 60 degree water through a radiator in your HVAC system. I know there are companies that can install these system but I can't recall any names off the top of my head.

    Fith, solid state storage. If you can swing paying $50/gig as opposed to $1/gig for storage space you can dramaticly cut down on your both your cooling bill and your electric bill.But at $50,000 per ter vs $1,000 per ter, it's going to take a while to recoup the costs.

    Sixth, custom server cases/cabinets. Traditional closets are great for cramming a lot of servers into a small area, but they about suck for heat management. You could fund a research project at any number of engineering schools to create a better storage solution.

    -Rick

    --
    "Most people in the U.S. wouldn't know they live in a tyrannical state if it walked up and grabbed their junk." - MyFirs
  3. Consult the experts... by stienman · · Score: 4, Insightful

    Get a professional electrician in that knows about peak charges.

    Older installations used to use giant flywheels, but not to limit peaks. They were used for power conditioning and limited power backup.

    I'd do an extensive survey before trying anything else. Buy or rent a power meter that does logging and graphing. Check everything out for a month - each phase and the current draw on each phase, and current draw on each rack (each computer if possible).

    Proper sequencing of cooling can drastically affect your power consumption. Never start your cooling motors when you're drawing a lot of power - motor startup is a huge peak. After doing a survey of your power needs you may be able to identify times when you can avoid turning the cooling system on which will lower your peak. For instance, before the daily peak, cool the data center down a few degrees more than usual. Then shut off one or more cooling system until after the daily peak. This can be tricky to correctly manage and implement, especially since it has to be automatic and failsafe.

    Alternately, shop around for your power. check with a few competitive companies and see if they offer a better deal.