How the Webb Space Telescope Got So Expensive
First time accepted submitter IICV writes "Ethan Siegel of Starts with a Bang has done some research on how and why the James Webb Space Telescope's price tag ballooned. Quoting: 'Something wasn't adding up. How could the telescope be more than three-quarters complete after $3.5 billion, but require more than double that amount to finish it? Also, how did the launch date get bumped by three years, to 2018? And how did 6.5 billion become a disastrous $8.7 billion so quickly? So I did a little digging around, and perhaps a little investigative reporting as well, and got ahold of a Webb Project Scientist who's also a member of the Webb Science Working Group.'" Whether or not you buy the argument that the money's well-spent (at $5 billion or $8 billion, or either side of these), even the work in progress is beautiful.
How the Web space telescope became so expensive? Connectivity through Comcast, no doubt.
Hmmm. And First Post?
If you want news from today, you have to come back tomorrow.
The whole project, with budget over-runs, is still cheaper than 1 month in Iraq...
How the Webb Space Telescope Got So Expensive?
Obviously it was the shipping and handling charges.
1st Corollary to Hofstadter's Law: It always costs more than you expect, even when you take into account Hofstadter's Law.
Hofstadter's original law actually only applies to time (not money). Typical usage: A couple years ago the NYC MTA Canarsie line "next train" countdown signs, originally a two year project, were running a couple years behind, and projected to take 5 years to complete.
You're doing something nobody has done before, inventing it as you go, and people expect you to know in advance how much it's going to cost. There are always unforeseen things that crop up.
And then there is the whole complexity of getting it funded in the first place. And the smoke and mirrors that come with that. The most fun we had was getting funding for the hardware but not the software. The project is one year over schedule, the hardware is done, but the software...
RogerWilco the Adventurous Janitor
Thank you for a very nice piece of investigative journalism. I summarize my understanding of it as follows:
The JWST budget did not include provision for technical and other problems that are expected to happen on large speculative projects such as this.
Oversight failed to act on warnings that budgets were being exceeded and schedules were drifting.
When oversight finally pulled the plug, parts of the project were near completion (implying that a 2014 launch date may have been possible).
Attempts to salvage any of the billions invested will incur significant additional costs due to loss of staff and the dissipation of knowledge, pushing any possible launch date close to 2020 and a budget four times the size of the original estimate.
Congress is shifting the blame entirely to NASA; seemingly avoiding responsibility for its part in appropriating public money without either due diligence or proper oversight.
Sound like business as usual.
If you reward lying, you will get more lies. The original budget was intentionally low-balled (i.e. it was a lie), and now the truth is coming out. But no one will be fired, no one will be punished, there will be no negative consequences for the liars. There will also be no consequences for the people that accepted the lies. No incumbent will fail to be reelected over just a few billion in overruns. Expect more massive overruns on future projects. There is no reason to expect anything else.
There are two commpeting forces at play here. Three if you include the people responsible for the budget.
The first and most obvious group is the scientists who first proposed the telescope and want to use it.
The second group are the people contracted to build it. These are the ones with all the power and the most to lose. Once the JWST is finished and launched they are (mostly) out of as job. As a consequence they have a selfish interest in making the design,development, testing and integration take as long as possible - simply to preserve their jobs and income. Now that's a fairly extreme description. I'm (almost) sure that nobody actually goes out of their way to sabotage it, or malinger. It's just that as with any project, there's always the possibility to improve things: tweak the spec. here, add another 0.05dB to a noise margin there ... and so it goes on; With no hard and fast deadline in the offing, there's nobody to say "it's absolutely got to be finished by <date>". Military projects in peacetime suffer exactly the same project creep and delays, for exactly the same reason.
The deadline is the key - that's why the moon landings happened on time. That's why wartime projects (when people are dying for lack of a solution) turbo-charge innovation. The JFDI attitude is paramount and without a launch date to work towards (or at least without a credible one, that absolutely MUST be met) the contractors are always going to be suggesting improvements, not overcoming delays and problems and finding more expensive options for problems.
politicians are like babies' nappies: they should both be changed regularly and for the same reasons
Since I submitted this story, I've actually RTFA'd and that's exactly what didn't happen.
Here's a timeline of events:
1. NASA says "we could make the JWST for $5.1 billion, and launch in 2014". Not "make and run for five years", the $5.1 billion only covers making the thing and putting it into space.
2. NASA's management fucks up, and an independent review panel finds that the actual price tag will be $6.5 billion, with a launch in 2015. This is NASA's fault.
3. However, the $6.5 billion number is contingent on NASA having $250 million to spend in 2011 and 2012 on important things like not laying off critical workers, and funding the fabrication of vital parts.
4. Congress does not provide that money, so the $6.5 billion number was never actually achievable anyway.
5. Now that NASA's fucked, climbing back out of the hole will cost an extra 1 - 1.5 billion dollars, because Congress didn't want to approve a total of 0.5 billion dollars over the next two years.
6. To add insult to injury, the number they're bandying about right now to show how much the project has gone over includes the cost of running it for five years, which the initial estimates did not. This adds nearly an extra billion on to the number.
At no point did NASA intentionally lowball the budget; if NASA's management hadn't fucked up, they could have made it. The initial cost overrun from $5.1 to $6.5 billion is NASA's fault, because NASA's been administrated by idiots for the last couple of decades.