stoborrobots writes: The Government Accountability Office has investigated the cost blowouts associated with how the Centers for Medicare & Medicaid Services (CMS) handled the Healthcare.gov project. It has released a 60-page report entitled Healthcare.gov: Ineffective Planning and Oversight Practices Underscore the Need for Improved Contract Management, with a 5 page summary. The key takeaway messages are:
  • CMS undertook the development of Healthcare.gov and its related systems without effective planning or oversight practices...
  • [The task] was a complex effort with compressed time frames. To be expedient, CMS issued task orders ... when key technical requirements were unknown...
  • CMS identified major performance issues ... but took only limited steps to hold the contractor accountable.
  • CMS awarded a new contract to another firm [and the new contract's cost has doubled] due to changes such as new requirements and other enhancements...

3 of 194 comments (clear)

  1. Technical People by TechyImmigrant · · Score: 5, Interesting

    Non technical people are not competent to commission technical work from technical people.

    If you (as a government or large company) don't have your own technical people on staff to oversee the process and comprehend or write the specs, you're doomed. The contractors know well how to milk a cash cow, simply by adhering to the specs written by people who don't understand how to write specs.

    --
    I should use this sig to advertise my book ISBN-13 : 978-1501515132.
  2. Re:in other words by ganjadude · · Score: 5, Interesting

    congress tried to delay it before the government shutdown remember? obama would not budge, causing the government shutdown.

    after the shutdown the site launched, and as expected obama changed his mind and delayed implementation anyway

    so the reason for the shutdown was that the democrats did not want a delay and wouldnt budge. then when the site launches and makes them look bad, the implement the delay anyway... yet they still blame congress for the shutdown. and based on your comment it seems some americans are still dumb enough to believe it

    --
    have you seen my sig? there are many others like it but none that are the same
  3. F-35 Joint Strike Fighter by tekrat · · Score: 5, Interesting

    Really, we want to complain about a website that cost a Billion? This is the United States Government, full of waste, fraud, no-bid contracts, and shit spread out out over every state so that ever senator and congressman has his slice of the taxpayer slush fund.

    Witness the F-35 Joint Strike Fighter, an aircraft nobody needs, trying to fill too many roles, and was supposed to save our armed services money by having one plane replace many planes.

    Except it's billions over budget, still doesn't work (and might never work), and is expected to cost more than a Trillion dollars before all is said and done.

    Meanwhile the aircraft is being usurped by drones, which are cheaper, easier to deploy, and may fill all the roles we'd ever need this crazy ass jet for. And we're trying so hard to make it stealthy, meanwhile as pointed out in a slashot article a few weeks back, long wave radar will find the plane just fine.

    And yet the Pentagon continues to shovel more money into the project because -- guess what, there's no "plan B". This is the people we depend upon to strategize for us in times of war, and they have absolutley no fall-back plan. Brilliant.

    --
    If telephones are outlawed, then only outlaws will have telephones.