Nuclear Plant Taken Down In Anticipation of Snowstorm
mdsolar writes Pilgrim Power Plant in Plymouth was taken offline in anticipation of the weekend snowstorm. According to a statement from Entergy, the owner of Pilgrim, the plant was taken off line in preparation of "a potential loss of offsite power or the grid's inability to accept the power Pilgrim generates." This is the second time this season the plant has been shut down due to storm conditions. On January 27 the facility was taken offline after the two main power transmission lines were knocked out by blizzard conditions. Although the transmission lines were restored within a few days, the plant remained offline until February 7 at which time it was reconnected to the grid.
An emergency measure when done after the fact.
He probably wouldn't post something about a 'renewable' going offline, based on his posting history.
That plant is not known for being run well.
More likely, they wanted to shut it down to cover their asses in case something bad happened, e.g. storm surge. Not a bad idea, considering.
there are 3 kinds of people:
* those who can count
* those who can't
Holy hell, it took roughly 11 days to repair the power transmission lines? Did anyone die from the cold?
If such a thing happened in Canada you can be sure we wouldn't take over a week to repair the government-owned power lines.
We could have a replay of this event as the Boston area is dealing with a similar weekend storm this week too.
The "national gird" is set up so they can handle the loss of a plant or two (or maybe even three) without disruption, it just causes the online plants to spin up stronger. If your power company is claiming to be National Grid, they're indicating that they're sometimes using power from outside the area they serve.
However, in this case, the customers don't lose power because the generation isn't there. Customers would lose power because the grid fails. Entergy has power from other sources or purchasing agreements to make up for this temporarily.
Similarly, it is unsafe (and illegal, technically) to run your nuclear powerplant with no access to the grid. If you have a coal plant that gets disconnected from the grid, you'd shut it down too with no way to generate revenue from burning additional fuel.
Devil's advocate to your misguided devil's advocate...The problem is the electrical grid not the source.
Sounds like this is a "preventative measure".
Normally there is some time between neutron capture and actual nuclear fission (I have heard a figure of 15 minutes). This means that even if the control rods are slammed in when the power transmission lines were cut the previous heat load would still be generated for a period of time. Often this means resorting to drastic measures to reduce the neutron flux to zero ASAP (certain salts are added to cooling loops which achieve this but requires a good flush to get rid of).
Controlled shutdown means the reactor can be restarted in "a couple of hours"
Emergency shutdown means the reactor can be restarted in "a couple of weeks"
Burnt once, twice shy...
...that it didn't melt down. We get it, MD, you don't like nuclear power.
Alcohol, Tobacco and Firearms should be the name of a store, not a government agency.
... my goddamn solar system goes offline every goddamn day for HOURS AND HOURS, and always during the coldest part of these frigid winter days...
Parent misses the point that giving the mdsolar troll a bone every now and then encourages his behaviour.
Local power lines routed through trees. High tension lines on rotting wooden towers. Welcome to the People's Republic of Massachusetts, where the buses are always on time, the subways never stop running, and town-owned sections of the sidewalk are always the first to be shovelled.
Pilgrim Power Plant in Plymouth was taken offline line Saturday in anticipation of the weekend snowstorm.
I can understand concerns about grid underservice...thats capitalism. What i cant understand is cycling down a nuclear facility because you're worried about power supplied from external source. you are a nuclear facility power is in and of your nature. This is the second time you've done this, so stop placating investors and be truthful: either the state of Massachusetts is no longer capable if funding a power grid that can endure normal weather patterns, or global climate change is an immediate concern we should all address.
Good people go to bed earlier.
How does using FF stop bad weather from taking out transmission lines?
And did you exchange a walk on part in the war for a lead role in a cage? - Pink Floyd.
Unreliable refers to Pilgrim's sorry history. http://www.patriotledger.com/a... It is typical of Entergy's "fleet."
France seems to handle their plants fine. And wind power and solar power have capacity factors so low than it won't work for grid generation without excess generation capacity and storage to begin with.
Both the top news you posted here and your second link in the parent post are about transmission grid failures. Not nuclear power plant failures. As for graceful powering up and down it can be done. France for example has nuclear power plants with load-following mode. The US doesn't bother with this because the faction of power generated with nuclear is low enough that it isn't worth doing the retrofits. As for the heat sink being too hot you would have the same problem with any other thermal power plant which uses a cooling tower. Coal, natural gas, whatever. It isn't a nuclear power specific problem either. It's a thermal power plant issue.
and paid for a "ROOF" - that way when it snows, it could keep running....but noooo... :)
The People salute you for your commonwealth's stewardship, comrade!
Relative terms can be missleading. The slowest cheetah is still much faster than the fastest turtle. While it may be among the worst nuclear plants it is still extremely reliable. From the article you referenced
Pilgrim performed at nearly 97 percent capacity in 2014
Maybe if they put Power lines underground they wouldn't come down every time there is a storm, which seems to be twice a week in New England
Bias revealed. Submitter hates Entergy.
Unreliable refers to Pilgrim's sorry history
From the linked article: "Pilgrim Nuclear Power Station in Plymouth will continue to be classified by the federal government as one of the worst performers among nuclear power plants in the country, at least for now, based on a recent inspection."
Which invites the question of how the best nuclear power plants in the country are faring?
This post may contain factual INFORMATION. Quick mod this down as a TROLL!!!
Actually, emergency or not, reactors have to be shut down for a few days. Just like they were in the case when power lines went down. When reactor shuts down, it is T-0, irrelevant of reason. It needs to wait for a few days until all the Xe-135 decays.
http://en.wikipedia.org/wiki/N...
These things need to decay before you can restart. If you try to be cleaver about it, especially with bad reactor designs, you end up with Chernobyl. Literally. (And if you don't understand what the above means, don't try to spin this as some sort of "nuclear is dangerous" bullshit. It's the same as cooling blast furnace at a smelter - you can't speed up cooling by using things like water, or you'll cause an explosion and people will die - it doesn't mean blast furnace is unsafe!).
So if you shut down proactively, and power lines go down or another plant goes down, you can restart the nukes as soon as power lines are repaired and before other plants are ready, if those suffer damage from the storm. All they did was proactive shutdown of excess capacity to deal with possible grid disturbances later. Imagine if grid connections collapsed to 2 other power plants and the nuclear plant, but nuclear plant grid could be repaired within a day but others took weeks.
This was done to increase reliability of the grid after the storm, not because of "omg, nukular plant and storm". Shameful on mdsolar that he tries to spin proactive action relative to grid stability as something that has anything to do with any single power plant.
Wait for it.... Tsunami !
Too bad MB wanted too much to melt snow. What do they teach the kids in school these days?
France has to shut down nuclear power plants every few years when there is a heat wave in Europe. Google is your friend.
The problem with load-following is economics. Nuclear power is already uneconomical. Load-following does not help.
It isn't a nuclear power specific problem either. It's a thermal power plant issue.
Ofc it is! Since when can a coal plant melt down?
Your wind/solar nitpicking is idiocy. Who cares about 'capacity' factors as long as a plant yields energy when it is needed or is planned for?
Actually, no one in the industry uses that term. It is only used by marketing droids after fanboys like you made it popular in the internet. The term used by power companies is load utilization, and it is not measured in % ... up to you to figure. Google might (or might not) be your friend.
Cost free eBook I read (by iBook/Kobo/Amazon/ObookO/Gutenberg etc.): "The Green Odyssey" by Philip Jose Farmer.
Not only is nuclear power economical, it's currently by far the most profitable investment you can make in a lot of countries.
Here in Finland, the best private investment in terms of ROI are nuclear reactors at Loviisa, followed by nuclear reactors at Olkiluoto. Everything else is far behind those. This is because once you repay the debt on the plant, you have about 50-60 years of pure profit with minimal expenses in comparison to amount of energy you can sell. And those plants were built several decades ago, so they're basically printing money for the owners right now.
Of course we have a functional infrastructure, reliable grid and ability to sell power to all of our neighbours which helps profitability of nuclear power plants with ~99% load utilization significantly.
Of course, if the United States has nine or more nuclear power plants, nine of them will be "among nine of the poorest performing nuclear plants" -- even if those plants have a exemplary record and exceed every safety requirement. If the United States had exactly nine nuclear power plants, each of them would be "among nine of the poorest performing nuclear plants" AND "among nine of the best performing nuclear plants"
Why is there an "insightful" mod and why isn't it "-1"? If I wanted insight, I wouldn't be reading
"Nuclear plan takes reasonable - or possibly even excessive - precaution." Eek. My skirts are all aflutter ...
Yeah, but that's like hating Verizon or Monsanto.
He may be on the wrong side of the nuclear debate, but the only people that like Entergy are Entergy execs.
Morons like yourself will always, even when it's nothing to do with shutting down or failure of a renewable power station, bleat on about "it's unreliable! what will you do when the wind stops, huh?".
Posting a cutout of a nuclear power station IS required. And again it's morons like yourself that make it a requirement. You appear to think that only renewables demand backup power, nuclear never. Therefore this incident which indicates that nuclear needs backup MUST be pushed forward so that there's even a TINY chance of it breaking through your idiocy that all power stations are unreliable and require backup.
You are whining about this because you don't want to consider nuclear unreliability.
This isn't news.
Why do I even visit this site anymore...
However it's out of action for maintenance or failure for about 40% of the time.
DAWES report includes many nuclear power plants assessed for utility.
Oh!... Plymouth in the US somewhere (apparently the Northwest, according to comments above). So not the Plymouth in the South West of England then. Okay, no worries - no snow coming our way, carry on...
(it would be nice if USians would realise most places in the US are named after places in and around the UK, the remainder are mostly taken from more native sources and so sound a bit different.)
Here in Finland, the best private investment in terms of ROI are nuclear reactors at Loviisa, followed by nuclear reactors at Olkiluoto
Source? I was under the impression Olkiluoto #3 was a colossal failure and 300% over budget. Oh yes, from wikipedia,
"Unit 3, an EPR reactor, is still under construction, but various problems with workmanship and supervision have created costly delays which have been the subject of an inquiry by the Finnish nuclear regulator Säteilyturvakeskus (STUK).[1] In December 2012, Areva estimated that the full cost of building the reactor will be about €8.5 billion, or almost three times the delivery price of €3 billion.[2][3] A license for a fourth reactor to be built at the site was granted by the Finnish parliament in July 2010,[4][5][6] but discontinued by the government in September 2014. TVO has the option to reapply for the license in the future.[7]"
Are you claiming at 300% over budget it has the among the best ROI? I mean even in Finland you could build out solar energy with a better ROI than a $10/WAC nuclear plant (or gas, oil, wood, steam, wind, biomass) nothing costs this much except a nuclear boondoogle.
Out of curiosity, what deaths have hydro caused?
You know, I'm not sure "we thought things were less bad than they were because we didn't even have a proper assessment process" isn't exactly a positive note in their favour.
Olkiluoto #3 is, as the name implies, the THIRD unit. Other two are the most profitable endeavours ever, after two units at Loviisa.
I can't find you the source right away, however this was a part of investigative story made by YLE, our state broadcaster. They were doing an analysis of profitability of investments, I believe as a part of their story on which of our traditional industries are competitive and which are not, and then they hit the fact that there were four extreme outliers in their statistics which were extremely profitable. Loviisa unit 1, Loviisa unit 2, Olkiluoto unit 1 and Olkiluoto unit 2.
Olkiluoto unit 3 is the experimental new reactor Areva was selected to build, and they failed at it. It's fairly obvious to even a casual observer that I could not have been talking about Olkiluoto unit 3 because it's not operating yet - as a result it can post no revenue.
Olkiluoto #3 is, as the name implies, the THIRD unit. Other two are the most profitable endeavours ever, after two units at Loviisa.
I can't find you the source right away, however this was a part of investigative story made by YLE, our state broadcaster. They were doing an analysis of profitability of investments, I believe as a part of their story on which of our traditional industries are competitive and which are not, and then they hit the fact that there were four extreme outliers in their statistics which were extremely profitable. Loviisa unit 1, Loviisa unit 2, Olkiluoto unit 1 and Olkiluoto unit 2.
Maybe this is true - but is rather irrelevant. I don't doubt that some nuclear power plant built at sometime somewhere was/is profitable. Those plants have been build at a time where electricity market was highly regulated in Finland. The price of electricity is determined by the least efficient plant (in terms of marginal cost) which is needed to satisfy demand. In the past, and without much competition this may have been a rather expensive source of power. Nuclear power plants only needed to be cheaper than this plant to be a good investment. Nowadays, this is unlikely to be true even in Finland.
Olkiluoto unit 3 is the experimental new reactor Areva was selected to build, and they failed at it. It's fairly obvious to even a casual observer that I could not have been talking about Olkiluoto unit 3 because it's not operating yet - as a result it can post no revenue.
But I guess it eats all profts from the other plants.
Actually, the grandparent is partially correct - he's describing what is called slow fission, and it's what makes fission reactors practical. Though to be fair, you're partially correct as well - you're describing fast fission (prompt criticality) which is what makes nuclear bombs possible. The difference between the two lies in the engineering, I.E. the presence of a moderator, the amount and type of nuclear materiel present, etc..., etc...
What makes you both partially correct is that there isn't a delay in fission, but a delay in neutron release.
Decay heat in reactors comes partially from these delayed neutrons, partially from the fission of daughter products. (Right after shutdown, the former predominates, over time they cross over until the latter predominates.)
No. Under normal operating conditions, about 7% comes from various delayed sources - but when the reactor is shut down, the neutrons creating those sources are essentially shut down as well. Thus, over time the amount of energy released from those sources falls off over time (reaching .02% of normal operating power within a week) as the delayed neutrons are exhausted and short half life fission products decay.
Actually the price of electricity in Finland is among the lowest in Europe. This is one of the chief reasons how our system works. You see, we have a lot of traditionally extremely energy-intensive industry related to forestry (i.e. paper, carton and cellulose production), metalworks (both smelting and advanced machining such as shipbuilding) and so on. As a result, one of the primary goals of the entire country's energy policy is to ensure that electricity would be as cheap as possible.
This kind of forward planning is what allows for those record profits. Not electricity prices, that are very cheap in Finland by European standards to the point that it was one of the chief reasons why most of the heavy industry stays in the country, and why modern energy intensive industries like heavy datacenters (i.e. Google) find Finland so interesting for their European operations.
Some other things you should understand before arguing on the topic of "eating profits".
1. Loviisa site is owned by a different power company, Fortum. Olkiluoto is owned by TVO. The third planned nuclear plant site is by a third company, Fennovoima at Pyhäjoki.
2. Financing in modern world is done through credit rather than through running profits.
3. Areva has actually agreed to fixed price delivery. Which is why Areva has done huge write downs for the plant. Most of the losses related to Olkiluoto 3 that TVO, the company that runs Olkiluoto site come from having no ability to produce power as planned and having to source energy elsewhere. Luckily we have solid interconnects with Russia (mainly Sosnovy Bor nuclear plant), Estonia (Narva's shale rock plant) and Sweden (Hydro across northern Sweden) to pick up the slack when needed.
4. Nuclear industry is considered so profitable here in Finland that third site by a separate company is in advanced planned stages. Fennovoima has selected a Rosatom reactor for a Pyhäjoki site just recently. To give you an understanding of how far decision making is on this, our government had anti-nuclear Green party as one of the smaller parties within it, and it ended up resigning from government when other parties, including much of opposition parties voted to proceed with the granting of necessary permits.
I see. You didn't get it when you learned themodynamics. A heat pump needs a cold reservoir to work. Much like a car needs a radiator. It doesn't matter if the car is gasoline or diesel powered. If the radiator isn't working and providing cooling for the engine either you shut down the engine or you melt the engine. Simple as that. If it was a coal power plant you would have to shut it down as well if the cooling water became too hot. Unless you want to wreck the power plant. There are alternative cooling systems to cooling towers but they are inefficient so they are not used in large scale thermal power plants. Also as you should remember from when you learned the Carnot cycle the higher the temperature you run an heat engine the more efficient it gets. So high efficiency thermal power plants, regardless of how they generate the heat, will always operate as close to the limits of the materials as they can.
Are you claiming that wind or solar have more availability than nuclear power? Try generating solar power in the night time or wind power when there is either no wind or too much wind (which forcibly shuts down windmills to prevent break down). Anyone with two brain cells knows renewables like solar and wind have less availability than nuclear power.
Yeah. The costs were higher because it was a prototype nuclear power plant. Besides a lot of people back then doubted Areva's construction cost estimates. Among the third generation nuclear power plants they are the most complex. The Westinghouse APs in China seem to be building more or less on schedule though. I think there was like 1-2 year delay at most.
As they get used to manufacturing these kinds of power plants the construction time and cost goes down.
I believe the biggest problem was identified as the fact that for Areva, this was actually the first project they managed on their own. Before that, another french state energy company did the top level management and coordination and Areva was more of an executor than manager.
Areva lacked know-how in this area, and that is where the biggest problem with the project lied.
You have the reading comprehension of used wad of chewing gum.
Absolutely incorrect - xenon accumulates in the reactor (to a level determined by a variety of complex factors) and poisons the reaction even during steady state operations, and this must be accounted for in the design of the reactor. (As I said, for an example of this, look up the first run of the Hanford plutonium production reactors - which were completely shut down by xenon poisoning.) Xenon does not magically appear or magically start absorbing neutrons just because power has been reduced or the reactor has been shut down.
I never claimed that xenon did not accumulate in all reactors currently in use - I merely pointed out that the behavior of civilian reactors with regards to xenon poisoning is the result of a deliberate design choice and operating philosophies, not a law of nature. Again, consider the difference in behavior between the first run of the Hanford plants and a modern plant.
No, you very obviously do not know what you're talking about.
There won't be meltdowns.
I see.
You never figured how a coal plant actually works. I suggest to visit one. They have guided tours.
No idea why you jump to wind and solar in the end of your post. I know like anybody else that solar works to 100% during daytime and to 0% at night time. What exactly is your point? (That is for PV)
I also know that wind plants don't produce electric energy when there is no wind, silly! Again, what is your point?
Thanx for pointing out the obvious, must have been important to you. You where not allowed to talk much as a child, I assume? Pitty! But time to get over it. Now you can talk, are allowed to tell long stories etc. So perhaps try to tell us something that matters. Thanx for the short introduction into Carnot again. There are so many people here on /. who get that guy wrong. Btw, very small correction: the heat is not that relevant. It is the heat difference.
So you want to claim, a coal plant can melt down like a nuclear plant, if it is not cooled, I mean you still want to claim that? Silly boy ...
Cost free eBook I read (by iBook/Kobo/Amazon/ObookO/Gutenberg etc.): "The Green Odyssey" by Philip Jose Farmer.
I never claimed otherwise. Are you really so fucking stupid that you think I am making that claim?
This is so fucked up and backwards I don't even know where to begin...
I'm done replying to you as you very obviously have no reading comprehension and no clue what you're talking about.
That's not how it happens, that's not how any of this happens...
Come and help me pay off my mortgage - small donations preferable! http://www.paymymortgage.com.au
Actually the price of electricity in Finland is among the lowest in Europe. This is one of the chief reasons how our system works. You see, we have a lot of traditionally extremely energy-intensive industry related to forestry (i.e. paper, carton and cellulose production), metalworks (both smelting and advanced machining such as shipbuilding) and so on. As a result, one of the primary goals of the entire country's energy policy is to ensure that electricity would be as cheap as possible. This kind of forward planning is what allows for those record profits. Not electricity prices, that are very cheap in Finland by European standards to the point that it was one of the chief reasons why most of the heavy industry stays in the country, and why modern energy intensive industries like heavy datacenters (i.e. Google) find Finland so interesting for their European operations.
The thing is: Cheap electricity prices make nuclear (and everything else) less economical. So the question still is why should nuclear plants be more profitable in Finland than elsewhere. Weren't the current plants not build by a government-owned power company (Imatran Voima Oy) which was then privatized later? Considering this, I assume that the existing nuclear plants in Finland were probably not really economical, but if nobody does an audit of how much this government-owned power company actually has spent when building these plants this will never become apparent. Looking at old press articles about how Loviisa started out has a hybrid of Sowijet and Western technology and needed costly repairs and changes, I somehow doubt that it was so economical as claimed.
Some other things you should understand before arguing on the topic of "eating profits".
....
Ok. But my point was that you should not sectively pick the successful projects while ignoring the cost of the failures when discussing the overall economics of nuclear. If the French tax payers pick up the bill for that disaster this is certainly good new for Fins, but does not really make nuclear more economical in the overall scheme of things.
1. Because even with cheap electricity prices, they are still very profitable. This is really not that hard to comprehend. Lower operating costs per unit of electricity produced = more profit.
2. Except that it's not "French tax payers" but "Areva". And Areva is in fact a multinational corporation, not a French government subsidiary even though approximately 90% of ownership is in French state's hands.
Their main problems right now are German decision to phase out nuclear power, reduction of nuclear design and building contracts due to Fukushima accident as well as Olkiluoto 3 problems. This has caused French government to increase capitalisation of the company.