Slashdot Mirror


Lockheed Martin Screwup Delays Delivery of Air Force GPS Satellites (bloomberg.com)

schwit1 writes: Incompetence by a Lockheed Martin subcontractor will delay the delivery of 32 new Air Force GPS satellites and will likely cost the government millions. Bloomberg reports: "Lockheed has a contract to build the first 10 of the satellites designed to provide a more accurate version of the Global Positioning System used for everything from the military's targeting of terrorists to turn-by-turn directions for civilians' smartphones. The program's latest setback may affect a pending Air Force decision on whether to open the final 22 satellites to competition from Lockheed rivals Boeing Co. and Northrop Grumman Corp. 'This was an avoidable situation and raised significant concerns with Lockheed Martin subcontractor management/oversight and Harris program management,' Teague said in a Dec. 21 message to congressional staff obtained by Bloomberg News. The parts in question are ceramic capacitors that have bedeviled the satellite project. They take higher-voltage power from the satellite's power system and reduce it to a voltage required for a particular subsystem. Last year, the Air Force and contractors discovered that Harris hadn't conducted tests on the components, including how long they would operate without failing, that should have been completed in 2010. Now, the Air Force says it found that Harris spent June to October of last year doing follow-up testing on the wrong parts instead of samples of the suspect capacitors installed on the first three satellites. Harris 'immediately notified Lockheed and the government' after a post-test inspection, Teague said in his message." So, the subcontractor first failed to do the required tests, then they did the tests on the wrong parts. Sounds like the kind of quality control problems we have seen recently in Russia and Japan. The worst part? The contract is a cost-plus contract, which means the U.S. tax payer has to absorb the additional costs for fixing the screw-up, not Lockheed Martin or its subcontractor.

68 comments

  1. cost plus contract by Lead+Butthead · · Score: 1

    And which fucktard in the government signed this stinker? Might this fucktard now be on Lockheed Martin's payroll now?

    --
    ELOI, ELOI, LAMA SABACHTHANI!?
    1. Re:cost plus contract by PolygamousRanchKid+ · · Score: 1

      . . . Let us be thankful that contractors don't make mistakes like this when building nuclear weapons . . .

      --
      Schroedinger's Brexit: The UK is both in and out of the EU at the same time!
    2. Re:cost plus contract by turkeydance · · Score: 4, Insightful

      cost plus contracts are about the only ones that are legitimately bid. most of the others are insider-type "fixes". historically, cost plus has meant three things: 1. if the US Government (contracting agency) changes anything after awarding the bid, cost plus activates. 2. if any other Government (China) changes any procurement procedures, cost plus activates. 3. finally, if an Act of God, War, or other devastation delays fulfillment, cost plus activates. yes, the US taxpayers pay more (they always do under most systems), but they get real competition in bidding. without cost plus protection, bidding would be limited to the insiders.

    3. Re: cost plus contract by Anonymous Coward · · Score: 1

      I dunno, the headline isn't bad:

      Today, due to component failure, instead of nuclear annihilation, the US and Russia pledge to investigate the simultaneous failure of Bobby's Bargain Basement Bomb Components.

    4. Re:cost plus contract by Anonymous Coward · · Score: 0

      Worse than that what fucktard signs a 'cost plus contract' that INCLUDES paying for costs due to screw ups by the manufacturer??? That is NOT what 'plus' means to me in a 'cost plus contract', where I have ALWAYS taken it to mean 'if I change a design requirement or otherwise make requests that were not clear as part of the original contract, including reducing the delivery time frame potentially leading to overtime THEN you are allowed to charge me for them.', not 'I'm paying for any old thing you can think of charging me for including YOUR fuck-ups!' Nobody in their right mind would agree to pay for that, but of course this is government so 'in their right mind' is unlikely and has to be assumed to be the opposite.

      It's not like these fuckwatts have been doing this for a day or two, we've been building & commissioning satellites for roughly 50 years, certainly by now they have the legal language down so that all parties are properly covered in the event of 'exigent circumstances' etc. due to the risks involved in this type of cutting edge technology & space travel, while allowing the manufacturers to make scad's of money anyway, while not taking us entirely to the cleaners.

      Hey, maybe Trump will get our money back....OOOOPS...let the 'Trump wars begin!' :-)

    5. Re:cost plus contract by Anonymous Coward · · Score: 0

      . . . Let us be thankful that contractors don't make mistakes like this when building nuclear weapons . . .

      The absence of unexplained mysterious mushroom clouds on the horizon is not absolute proof of your hypothesis.

    6. Re:cost plus contract by The+Grim+Reefer · · Score: 1

      1. if the US Government (contracting agency) changes anything after awarding the bid, cost plus activates. 2. if any other Government (China) changes any procurement procedures, cost plus activates. 3. finally, if an Act of God, War, or other devastation delays fulfillment, cost plus activates.

      I don't know anything about cost plus contracts, but of the three things you listed, incompetence/negligence doesn't appear to activate cost plus.

    7. Re:cost plus contract by ThermalRunaway · · Score: 2

      This is not correct. Cost Plus means the contractor is paid for actual work done plus either a fixed fee or an award feed... thus CPFF or CPAF contract types.

      Cost plus contracts are NOT the only ones bid legitimately... its normally the opposite. if you know you are you are going to get paid for your actual hours worked, you bid as low as you can justify and then incur over runs later for "risks"', etc.

      Point (1): no cost plus never "kicks in" like this. Even in other contract types if anything is changed you can renegotiate the cost.

      Point (2): WTF does this even mean....

      Point (3): Wrong again. nothing "activates". The contractor is paided for actual hours worked.. thus the "cost" part of cost plus. The "plus" part is the fee paid... basically profit.

      Example: You now lawns. You quote someone $50 to mow their lawn. This would be Fixed Price. You take however long you want to now the lawn, and you get $50.

      You quote someone $25 per hour for your labor and estimate it will take 2 hours to mow the lawn. This would be cost plus. You might add something like.. if I do a good job I also get $10 bonus at the end.. this would be cost plus fixed fee.

    8. Re:cost plus contract by rtb61 · · Score: 1

      Think of the lowest tender when you talk about nuclear weapons. Just to make you feel that little bit cosier keep in mind defence contractors first priority is to executive bonuses, than shareholder returns and then maintaining staff and somewhere in no mans land, defence of the country. If they can produce cheap crap that fails with maximum profit margins and get away with it, they will and they will do it on purpose, so they can replace that crap with, more crap.

      When defence contractors first priority is not defence of the country, than the people who contract to them are corrupt morons. So how many failures do US defence contractors manage to get away with now (keep in mind, not by accident but specifically on purpose, to charge more to fix those purposeful fuck ups). How long before the US manages to blow itself up with a nuclear weapon with the corporate executives involved wandering off with a golden parachute. You can bankrupt the nation and wander off laughing so why can you blow it up, keep in mind examples where executives already get away with it, oil drilling rigs and coal mines any one.

      --
      Chaos - everything, everywhere, everywhen
    9. Re:cost plus contract by K.+S.+Kyosuke · · Score: 1

      How would you know? They're not being tested anymore.

      --
      Ezekiel 23:20
    10. Re:cost plus contract by RespekMyAthorati · · Score: 1

      WOOOOSH!

  2. Who wrote this title? by Anonymous Coward · · Score: 0

    Harris made the mistake, why does the title say "Lockheed Martin Screwup Delays Delivery of Air Force GPS Satellites"?

    1. Re:Who wrote this title? by Anonymous Coward · · Score: 1

      Doesn't the buck stop with the prime contractor?

    2. Re: Who wrote this title? by Anonymous Coward · · Score: 0

      Why? Shouldn't it stop with the government contracting officer then?

    3. Re:Who wrote this title? by Anonymous Coward · · Score: 1

      Actually, it stops with the Contracting Officer on the government side, but the vast majority of them are incompetent, corrupt, or both.
      Drain the fucking swamp!

    4. Re:Who wrote this title? by Anonymous Coward · · Score: 1

      Drain the fucking swamp!

      They tried to drain the swamps in the DC metro area many, many years ago. Problem was the swampy waters were replaced with the most vile creatures on the planet, politicians.

      Drain the swamp? How about we re-flood the swamp and drown all of the bastards.

    5. Re: Who wrote this title? by PoopJuggler · · Score: 2

      Nuke the entire site from orbit. It's the only way to be sure.

  3. And there won't be any accountability by HangingChad · · Score: 2

    Maybe a couple low level contract managers will lose jobs, but even that's doubtful. Certainly no one will get prosecuted. The taxpayers are out millions, Lockheed Martin can continue bidding government jobs and don't even have to pay the money back.

    --
    That's our life, the big wheel of shit. - The Fat Man, Blue Tango Salvage
    1. Re: And there won't be any accountability by Anonymous Coward · · Score: 0

      Donald Trump will fix it. He will tweet something mean and cow them into submission.

    2. Re: And there won't be any accountability by ColdWetDog · · Score: 1

      Donald Trump will fix it. He will tweet something mean and cow them into submission.

      He'll moo at them? I've seen some cows who appear, at first blush, smarter than our current president ,but I don't think you can tweet with hooves.

      --
      Faster! Faster! Faster would be better!
    3. Re: And there won't be any accountability by Anonymous Coward · · Score: 0

      Why would anybody be prosecuted? This isn't a Napoleonic code country, where every mistake must be prosecuted.

    4. Re: And there won't be any accountability by Anonymous Coward · · Score: 0

      Well, that's why cows will have to work with immigrant oxpeckers to do all of their tweeting for them.

      (It's a bird, not a literal ox pecker.)

    5. Re: And there won't be any accountability by ArmoredDragon · · Score: 1

      He'll moo at them? I've seen some cows who appear, at first blush, smarter than our current president ,but I don't think you can tweet with hooves.

      That...can't be true...we have many demons in Washington, and they manage to type with hooves all the time.

    6. Re:And there won't be any accountability by thegarbz · · Score: 1

      What's the alternative? Project finished on time, and on budget. Government moves to roll out the next one, Lockheed Martin get given it and life carries on.

      In the case of these style of government contracts it becomes silly to consider the contract at hand. Instead simply consider everyone involved to simply be a salary member of government staff. All that's really happening is the project is slightly behind delaying the next one. The tax payer is still breaking even as there's never a period where Lockheed and Boeing are not working on some government contract.

      Heck even the lowly disposable engineers simply move from one company which was awarded the project to the other.

    7. Re:And there won't be any accountability by SvnLyrBrto · · Score: 1

      The alternative is to ban "cost plus" contracts. Screw up and overrun the costs specified in you bid? Tough cookies. Eat it on your P&L leader, and do a better job bidding next time.

      Another, at least as good and maybe better, option is antitrust. Break up the globs back into Northrop, Hughes, General Dynamics, Lockheed, Marietta, Glenn Martin Co, Grumman, McDonnell Aircraft, Douglas Aircraft, Convair, North American, Republic, Boeing, Rockwell, and so on... so that there are a dozen manufacturers actually bidding competitively for contracts with incentives to keep costs under control, lest the contract goto a more reliable competitor.

      After all, when there are only two choices, why *Should* Lockheed Martin (from their perspective) deliver a fully-functional air or space craft as promised, and on-time and on-budget. What's the government going to do after all, go to Northrop "2 billion dollar stealth bomber" Grumman?

      --
      Imagine all the people...
    8. Re:And there won't be any accountability by sh00z · · Score: 1

      The alternative is to ban "cost plus" contracts. Screw up and overrun the costs specified in you bid? Tough cookies. Eat it on your P&L leader, and do a better job bidding next time.

      Another, at least as good and maybe better, option is antitrust. Break up the globs back into Northrop, Hughes, General Dynamics, Lockheed, Marietta, Glenn Martin Co, Grumman, McDonnell Aircraft, Douglas Aircraft, Convair, North American, Republic, Boeing, Rockwell, and so on... so that there are a dozen manufacturers actually bidding competitively for contracts with incentives to keep costs under control, lest the contract goto a more reliable competitor.

      After all, when there are only two choices, why *Should* Lockheed Martin (from their perspective) deliver a fully-functional air or space craft as promised, and on-time and on-budget. What's the government going to do after all, go to Northrop "2 billion dollar stealth bomber" Grumman?

      You haven't thought out the consequences. If these are all bid a Firm Fixed Price (the alternative), every bidder is going to pad their costs to compensate for the possibility of things going wrong at some point during the development . Depending on the likelihood of that (cutting-edge technology, etc.) this will be anywhere from 15 to 30 percent of the original estimate. Would you rather pay 20% more overall, or take the chance of a 10% overrun?

  4. I used to work for Harris Corp by Anonymous Coward · · Score: 0

    And let me tell ya, it was quite the shitshow.

  5. Harris? Incompetent? Naaah by Anonymous Coward · · Score: 0

    Ever look up the epic failure of Harris' software-defined radio contract?

  6. Bad journalism by jcbarlow · · Score: 3, Insightful

    This is just total nonsense: "The parts in question are ceramic capacitors that have bedeviled the satellite project. They take higher-voltage power from the satellite's power system and reduce it to a voltage required for a particular subsystem" Nope, wrong, try again.

    1. Re:Bad journalism by dstyle5 · · Score: 1

      Maybe that definition was obtained from a Harris document, might explain a few things.

    2. Re:Bad journalism by Anonymous Coward · · Score: 0

      This caught my eye, they make it sound technical but that's not really what caps do, unless it's part of a powersupply and it's the weak link but again not sure how ceramic caps are involved.

      Any EE's out there want to chime in?

    3. Re:Bad journalism by networkBoy · · Score: 5, Informative

      Noise filtering.
      Often these DC-DC stepdown converters can leave lots of ringing on the DC Rails (bot input and output). The capacitors (chosen for their ability to both absorb the peak and fill the trough of the ring at the requisite frequency) are responsible for making that DC nice and smooth.
      When they fail it can be an open (common, and problematic) in which case the downstream components and assemblies are subjected to EMI and ring noise that may be out of their tolerance and thus degrade performance (or ultimately fail them); or the caps can fail shorted, which more often than not quickly becomes an open rather violently... unless the power supply dies from being shorted first.

      there's the easy reader version.

      --
      whois gawk date unzip strip find touch finger mount join nice man top fsck grep eject more yes exit umount sleep dump
    4. Re:Bad journalism by Anonymous Coward · · Score: 0

      I agree it's bad journalism but there is a specific way to use capacitors to reduce voltage (not that it applies here). Look at using capacitors as an AC voltage divider. http://www.electronics-tutorials.ws/capacitor/capacitive-voltage-divider.html

    5. Re:Bad journalism by thegarbz · · Score: 1

      Nope, wrong, try again.

      Oh I take it you work for Lockheed Martin and therefore have insider knowledge of the exact circuit involved and therefore know with some certainty that the powersupply is not of a divided AC type or switch capacitor regulation type or any of those other tuned circuits where capacitors are used to adjust and regulate the voltage of supply.

      Thanks for the insider info.

    6. Re:Bad journalism by thegarbz · · Score: 1

      It could also be an AC supply (unlikely on a satellite) but there are circuits which use purely capacitive elements for voltage regulation or an LC network or something similar.

      Again I don't expect that in a satellite. But then I have no idea about what they are building.

    7. Re:Bad journalism by Agripa · · Score: 1

      In this case, they must be the input and output capacitors of a switching power supply.

      Ceramic capacitors are only used this way in applications which can support the extra cost because large ceramic capacitors are very expensive. There advantages are very low ESR and ESL, high ripple current rating, and long life. Unfortunately their large physical size combined with brittle construction creates extra reliability issues and special mounting considerations are required. I am surprised that an aerospace manufacturer would have a problem with them though.

    8. Re:Bad journalism by networkBoy · · Score: 1

      You are correct, I have a line conditioner for my scope and atomic clock (admittedly a low end rubidium model) that is only a big-assed inductor and a capacitor. Works great at cleaning up AC, but I did assume DC-DC in my post since this was space-based GPS stuff and AFAIK the power bus on those is DC only.

      --
      whois gawk date unzip strip find touch finger mount join nice man top fsck grep eject more yes exit umount sleep dump
  7. Subcontractor? by Anonymous Coward · · Score: 0

    OK, time to name names... this subcontractor that skipped the testing, then did the wrong testing 6 years late...
    Who are they? Are then even a domestic firm? (I have my theories....)

    1. Re:Subcontractor? by Stormy+Dragon · · Score: 2

      The subcontractor was named...

    2. Re:Subcontractor? by thegarbz · · Score: 1

      I know reading the summary isn't really a thing but this is ludicrous. Not only was the subcontractor named but they were done so 4 times.

  8. If you believe... by Anonymous Coward · · Score: 0

    ...they put a man on the moon.

  9. Military contracts by Anonymous Coward · · Score: 0

    Technology involved are cutting edge and there is no accounting for hidden costs upfront. That's why government PAYS for select number of companies to build prototypes for contract bids. They don't want the companies going bankrupt spending millions on prototypes and not win the bid.

  10. Yes: Cost plus does not mean unlimited budget by Anonymous Coward · · Score: 1

    I'm a veteran of several federal and various state contracts. As turkeydance described, cost plus doesn't mean spend whatever the hell you want. Generally even with cost plus you have to get a change order to approve the additional costs, basically an addendum to the original contract. In my experience they're absolutely necessary because the client (the government) frequently changes requirements midstream. About half the time it's because of changing leadership/priorities and even changing laws. The other half of the time it's because the requirements you bid against had nothing to do with what they actually wanted (some agencies are worse about this than others).
     
    I'm not saying that the contracting system isn't gamed all the time, it is. But just as much blame lies with the way the government drafts requirements, bids the contracts and (more importantly) manages them. I had one contract I worked where the admin in charge of acquiring software licenses didn't get us the required license for nine months, _NINE_. We had to have the software to do the work and tried everything we could to get it legally. We partnered with the vendor all the time and they finally agreed to float us a license so we could at least get some work done but we were not allowed to do that because the license was not acquired through a GSA approved vendor... even though it was was free. It was the most mind numbingly stupid thing I've ever had to deal with in my consulting career.

    The bigger problem with these large military contracts is they are so big/specialized that only Boeing, Lockheed and Northrop Grumman can even think about bidding on them... beyond technical expertise you have to demonstrate that you have the capital and financial reserve to actually see the project through so it's impossible for someone to "disrupt" the system. Even SpaceX would probably have a problem meeting the financial requirements for this contract (launch vehicles are peanuts compared to the cost of military satellites). So even if Lockheed completely f*cks this up, they know the chances they'll actually lose it are pretty slim (witness the disaster that is the F-35). You'll see the government try scare the big three a little by soliciting bids from EADS, BAE, etc. The reality is they're never to going to source something this critical to a company outside the US and the "outsiders" know this. The replacement for the KC-10 is a perfect example of this. Airbus invested heavily to bid a variant of the A330 that most agreed was superior to the Boeing 767 variant but.. "Merica" so Boeing won. EADS isn't going to make that mistake again. So, they make a token proposal and then withdraw because it's not worth their time (like EADS did when asked to submit a proposal for the AF-1 replacement). And we're stuck footing the bill for boon-doggles like this.

  11. Getting paid more for screwing up... by Sulik · · Score: 1

    The more you screw up, the more money you get paid... Hmm, maybe we do need someone like Trump to negotiate those contracts...

    --
    Help! I am a self-aware entity trapped in an abstract function!
    1. Re:Getting paid more for screwing up... by bigwheel · · Score: 1

      "The more you screw up, the more money you get paid..."

      If I remember correctly, cost-plus basically says that the government will pay the costs of fixing the overruns (labor, materials, etc) but the company does not get any additional profit/fee. This allows a bid to be closer to reality, rather than each bid having to be padded to make up for eventual mistakes. It also gives the government a way to alter requirements without the company taking them to the cleaners for the contract mods.

  12. I'll do it cheaper. by Anonymous Coward · · Score: 0

    From the article

    In an Air Force list of priorities that lacked funding for this year, the service said it needed $100 million for GPS III “capacitor repair/replace.”

    I'll do it for $10 million (and I'll even provide my own soldering iron from Radio Shack).

    1. Re:I'll do it cheaper. by The+Grim+Reefer · · Score: 1

      I'll do it for $10 million (and I'll even provide my own soldering iron from Radio Shack).

      I hope it doesn't fail. Building a time machine to get a replacement soldering iron from Radio Shack is going to cost you more than $10 million.

    2. Re: I'll do it cheaper. by Bing+Tsher+E · · Score: 1

      I can drive over to Radio Shack tomorrow and get a soldering iron, if you insist. It's about a ten minute drive. Mind if I stop at the bank first and maybe to White Castle on the way for lunch?

      The small midwestern town I live on the outskirts of does still have a Radio Shack. I can buy assorted parts and tools and stuff. They even stock Arduinos and Shields, though they're way overpriced.

    3. Re: I'll do it cheaper. by poofmeisterp · · Score: 1

      I can drive over to Radio Shack tomorrow and get a soldering iron, if you insist. It's about a ten minute drive. Mind if I stop at the bank first and maybe to White Castle on the way for lunch?

      The small midwestern town I live on the outskirts of does still have a Radio Shack. I can buy assorted parts and tools and stuff. They even stock Arduinos and Shields, though they're way overpriced.

      Wow. I'm on the outskirts of Greater Cincinnati and they got rid of the last Mobile Sh... er Radio Shack a couple of years ago. Amazing. I wonder who the actual owner is!

  13. The Donald will fix their wagon by lophophore · · Score: 1

    Trump, whether you hate him or just strongly dislike him, will probably be tweeting about this tomorrow and LMCO will be up sh!t creek.

    --
    there are 3 kinds of people:
    * those who can count
    * those who can't
    1. Re:The Donald will fix their wagon by RespekMyAthorati · · Score: 1

      Trump, whether you hate him or just strongly dislike him, will probably be tweeting about this tomorrow and LMCO will be up sh!t creek.

      As if.
      Tomorrow he will be tweeting about how those mean old judges won't bend to his will, or about how ugly some female critic is.

  14. The worst part? by thinkwaitfast · · Score: 1

    No no no. That's the best part. Depending on you POV.

  15. Just use the Galileo navigation system instead by ffkom · · Score: 1

    The US will probably need all that tax-payers money elsewhere to build the wall to Mexico, so why not use the European Galileo Satelite Navigation instead - which already provides for much better spatial resolution?

    1. Re:Just use the Galileo navigation system instead by Anonymous Coward · · Score: 0

      Unfortunately Galileo is only half deployed, mainly because it's project delays are even worse than the GPS Block III. For safety critical systems, it is highly beneficial to have 2 independent systems so that failure of an entire system does not cause a fault.

    2. Re:Just use the Galileo navigation system instead by slew · · Score: 2

      The US will probably need all that tax-payers money elsewhere to build the wall to Mexico, so why not use the European Galileo Satelite Navigation instead - which already provides for much better spatial resolution?

      At least they flagged a potential reliability problem with GPS *before* they were launched. ESA is still trying to figure out what the reliability problem with their clocks might be...

      Unfortunately, (or fortunately) space is hard...

    3. Re: Just use the Galileo navigation system instead by Anonymous Coward · · Score: 0

      Because it's only half complete and has its own major problems,in that the atomic clocks keep failing,some of them are down to one or two working clocks already,they start of with 6 each !!

    4. Re:Just use the Galileo navigation system instead by Sir+Holo · · Score: 1

      ... At least they flagged a potential reliability problem with GPS *before* they were launched. ... Unfortunately, (or fortunately) space is hard...

      It is fortunate for the failure analysts. When a satellite is nearing launch and there is an issue with some part – that is when the money hose opens wide, and the USAF SMC's failure analysis lab (an FFRDC) is called upon, the money just gushes. They throw every analysis technique at the thing, whether it is appropriate or not. And they punish employees who solve the problem too quickly. I have personally been commanded to, "Go back and keep working on it for a couple of more weeks." That's just one example.

      You see, at a failure analysis lab supporting anything DOD, Program fuck-ups are very good for business. The managers tell basically all employees to drop their current work and just bathe in that sweet, sweet FA "root-cause failure analysis" money. No matter whether your technique can help – just do something with it.

      It is the craziest thing I have seen in my career. Space is expensive because it is expensive. This FA aspect is a nutty drain on the US Federal budget.

  16. Stupid H1bs by Anonymous Coward · · Score: 0

    I'm guessing this delay is probably caused by h1bs

  17. Harris by fred133 · · Score: 3, Informative

    Apparently, Harris makes more on their Stingray II units than these sub-assemblies for Lockheed.
    I'm sure the lead time on a StingRay is 7~10 working days for delivery, or overnight if you want to pay for the expedited freight.
    Obviously they have no scruples.

  18. Duplicate system? by Zoxed · · Score: 1

    Don't worry: the EU GPS system https://en.m.wikipedia.org/wik... will soon be live, so there will be no need to fund a duplicate US system. You can save yourselves some money ;-)

  19. "Here’s How Projects Usually Work" by Anonymous Coward · · Score: 0

    See this cartoon explanation of "Here's How Projects Usually Work", in the top of the middle column.

    "The open source version" was the best.

  20. Obscene Incompetence by LeftCoastThinker · · Score: 1

    Typical government employees pissing away taxpayer dollars. No business in their right minds would absorb the costs of errors committed by a supplier, and Trump should have the head of the bureaucrat who signed off on this contract on a platter. At minimum the industry standard of "if you screw it up you fix it on your dime" should be in every contract... Maybe this will change with an administration that actually ran a business instead of a community organizer... we sure have been getting the shaft for the last 40 years.

    --
    If you disagree, please post your argument. (-1, Overrated) isn't your personal censorship tool for views you don't like
  21. Not so bad by nospam007 · · Score: 1

    "Incompetence by a Lockheed Martin subcontractor..."

    Under the new so-called administration, ignorance and incompetence is a boon.

    1. Re:Not so bad by RespekMyAthorati · · Score: 1

      Under the new so-called administration, ignorance and incompetence is a boon.

      As long as you refer to it as "alt-wisdom" and "alt-competence".

  22. A 'GPS Holiday' by Cmdln+Daco · · Score: 1

    For purposes of promoting more self reliance, I propose the Government institute a 'GPS Holiday.'

    Every few months, at some random point, the GPS system should be switched off for a few hours.

    It would help assure that humanity not become vulnerable to a navigation system that could tumble down at any time.

  23. Ummm this is Harris's fault by Anonymous Coward · · Score: 0

    If you read TFA Harris fucked up hard here. OP has a clear bias / hatred towards LM

  24. um, nope... pay attention by Anonymous Coward · · Score: 0

    The government contracted with LockMart for the GPS satellites. PERIOD. FULL STOP.

    The fact that LockMart decided to contract with Harris for a component only means that LockMart was responsible to make sure Harris did the job properly [as LockMart was responsible to do had it made the parts itself in-house]. LockMart is fully responsible for the whole thing. If they chose to farm-out a component or a sub-assembly to some vendor and then failed to properly communicate the specs to that vendor, or failed to supervise that vendor or failed to verify the work of that vendor, etc it's LockMart's failure. The government is not buying capacitors from Harris, it's buying complete functional birds from LockMart.

    Now, if you want to shift blame, the one place you COULD shift it to is the federal government. This same government has over many years purchased many systems from LockMart who almost always under-performs while being over-budget and behind schedule. They probably should no longer be considered an acceptable/legitimate vendor. At this point, it's getting silly to have the government buy ANYTHING from any part of LockMart that is not the Skunk Works (Which did marvelous work decades ago on the F-117). Oh, and I have first-hand experience here having worked as a subcontractor of LockMart.

  25. *beathes in* by poofmeisterp · · Score: 1

    Here we go again...

    <sarcasm>
    You can't apply that title to the article. It's not Lockheed's fault. They have never done anything wrong. They use subcontractors for everything but the choosing of subcontractors. Hell, maybe that's even automated now. Change the title!!! </sarcasm>