Slashdot Mirror


Engineering Experts Knew Italian Bridge Had Corrosion Problems Before It Collapsed, Report Says (apnews.com)

McGruber shares a report: Engineering experts determined in February that corrosion of the metal cables supporting the Genoa highway bridge had reduced the bridge's strength by 20 percent -- a finding that came months before it collapsed last week, Italian media reported Monday. Despite the findings, newsmagazine Espresso wrote that "neither the ministry, nor the highway company, ever considered it necessary to limit traffic, divert heavy trucks, reduce the roadway from two to one lanes or reduce the speed" of vehicles on the key artery for the northern port city. A large section of the Morandi Bridge collapsed Aug. 14 during a heavy downpour, killing 43 people and forcing the evacuation of more than 600 people living in apartment buildings beneath another section of the bridge.

72 of 141 comments (clear)

  1. The other mistake by SuperKendall · · Score: 3, Interesting

    If corrosion weekend the cables by 20% of so, it seems like the original design didn't leave nearly enough margin for error!

    I imagine they were not as concerned with 20% weakening thinking they had much more leeway.

    --
    "There is more worth loving than we have strength to love." - Brian Jay Stanley
    1. Re:The other mistake by Anonymous Coward · · Score: 1

      I Am Not An Engineer so there's probably more involved, but "20% weakening = collapse" (as it has been implicitly presented here) does sound like they were asking for it.

    2. Re:The other mistake by fredgiblet · · Score: 3, Interesting

      Read the wiki article on the bridge. They've been fighting it's design for it's entire life and were even starting to prepare a replacement.

    3. Re:The other mistake by Freischutz · · Score: 4, Informative

      If corrosion weekend the cables by 20% of so, it seems like the original design didn't leave nearly enough margin for error!

      I imagine they were not as concerned with 20% weakening thinking they had much more leeway.

      It’s not just that, the bridge was hopelessly overloaded by traffic. There is a longstanding bypass project which has been fiercely opposed by the Five Star Movement for years. The Five Star Movement’s leaders, who now run Italy, actually cracked jokes about warnings that this bridge might collapse at regular intervals since the first warnings in 2012 or 2013. They are now trying to blame the EU (which gave them money for infrastructure sanitation) for the whole ugly mess.

    4. Re:The other mistake by bobbied · · Score: 2

      Time to accelerate those replacement plans I guess.

      --
      "File to fit, pound to insert, paint to match" - Aircraft Maintenance 101
    5. Re:The other mistake by bobbied · · Score: 1

      If corrosion weekend the cables by 20% of so, it seems like the original design didn't leave nearly enough margin for error!

      I imagine they were not as concerned with 20% weakening thinking they had much more leeway.

      But I'm inclined to believe that they thought they had enough margin in the bridge to keep using it. The question is if they didn't understand the structural design well enough to know that 20% was dangerous, or that they underestimated the loss of strength.

      Likely, the issue is a mixture of both. The engineers likely missed something important in the bridge's weakened state and the structure was substandard for the conditions. Much like the bridge that fell into the Mississippi river in the USA recently, which had structural decencies which where under estimated, and was loaded more than expected.

      --
      "File to fit, pound to insert, paint to match" - Aircraft Maintenance 101
    6. Re:The other mistake by Immerman · · Score: 5, Insightful

      It's been a lot of years since engineering school, but I seem to recall the recommended safety margins for most things were 100%-500%, so yes, a 20% weakening causing collapse would be a symptom of serious under-engineering.

      However, Wikipedia says this bridge is 51 years old, and that engineers have been expressing concern over its safety since the early 90s, with numerous other static and dynamic weaknesses being uncovered over the years, due to both degredation, and weakness in available computer modeling in the 60s.

      Apparently traffic has quadrupled since it was built as well, so it's probably been under a lot more stress than it was really designed for. And to top it all off, eye witnesses say it was struck by lightning just before the collapse - and I would imagine conducting that kind of amperage (~30kA typical) could heat a cable enough to weaken it considerably. You'd think good engineering would factor in lightning strikes on a tall bridge like this, and they probably did, but it was probably just one stress too many on an old bridge.

      --
      --- Most topics have many sides worth arguing, allow me to take one opposite you.
    7. Re:The other mistake by Thelasko · · Score: 4, Interesting

      AvE posted a great video on this bridge. The designer of the bridge didn't like adding extra reinforcing. This was probably for aesthetics. This made maintenance of the bridge difficult as structural components couldn't be repaired while the bridge was in service.

      --
      One of our competitors trademarked the term "hypothesis". From now on, we will call them "boneheaded ideas".
    8. Re:The other mistake by SuperKendall · · Score: 1

      Thanks, I actually did skim through the article for something like that but missed a Wiki link if it was there. I wonder how many other bridges are under-designed and just waiting to spring... You'd hope governments around the world would take events like this as a wake-up call to pay more attention to assessments.

      --
      "There is more worth loving than we have strength to love." - Brian Jay Stanley
    9. Re:The other mistake by iMadeGhostzilla · · Score: 2

      I've read about an engineering principle they used in England in the Middle Ages to make bridges safer: bridge constructors were required to sleep for two weeks under the bridge after it was constructed. With their families.

    10. Re:The other mistake by Anonymous Coward · · Score: 1, Funny

      Thanks, I actually did skim through the article for something like that but missed a Wiki link if it was there. I wonder how many other bridges are under-designed and just waiting to spring... You'd hope governments around the world would take events like this as a wake-up call to pay more attention to assessments.

      America's bridges are safe. President Obama spent $1 trillion on shovel-ready projects to fix all our infrastructure issues.

    11. Re:The other mistake by mikeiver1 · · Score: 4, Insightful

      Though I generally agree with your assessment of the issues there are a few I can take an alternate view of.

      First is that the strike to the cables would not have lasted long enough to cause heat induced weakening of them, But... The high current upon entering the the wet concrete could have caused the water to flash over to steam and maybe induce cracking in the structure.

      Second is the rebar embedded in the concrete supports has definitely corroded leading to weakened bonding and compromised structure internally. All concrete structures suffer this issue over time. Some deal with it by using epoxy coated rebar, some use composite rebar, and others use stainless steel to stave off this inevitable failure.

      Third is that the bridge was carrying four times the original traffic it was designed for and at speeds likely far in excess of those thought prudent at the time of design and build. This again added to the stressed induced on the structure and I would submit accelerated its failure.

      It is very likely that there were one or more engineers blowing the caution horn for some time now. It is also likely that they were flatly ignored, removed from the job, or sent elsewhere to silence them. Nice to see that the higher ups that lost their jobs at Morton Thiokol found new places to work and ways to kill others.

    12. Re:The other mistake by Anonymous Coward · · Score: 1

      Ponte Morandi...opened on 4 September 1967. So, provable safe since 18 September 1967. No need to revisit the issue, eh?

    13. Re:The other mistake by DarkOx · · Score: 1

      Not a civil or structural engineer but I know for roofs and stuff you usually build for 1.4 times the estimated required carrying capacity (weight of covers and potential snow loads etc). That is 1.4 times the max weight you ever think you'd need to support.

      Assuming the same convention is used for bridges; a 20% weakening still means it would be adequate to support loads it was designed to carry. However from the sounds of things it was also over loaded. Taken those two issues together -> problems.

      Still the headline may or may not be misleading. For example all kinds of bridges in this country are classified as deficient; but that just mean they don't meet certain safety margins - not that anyone thinks they are in danger of failure. If one did fail though people would no doubt say "engineers knew there were problems."

      I guess the take away here is those safety margins exist for a reason - its good to keep them as it prevents disasters like this from happening!

      --
      Repeal the 17th Amendment TODAY! Also Please Read http://www.gnu.org/philosophy/right-to-read.html
    14. Re:The other mistake by Anonymous Coward · · Score: 1

      Take a closer look at the fragments of the bridge. There is almost no rebar in the concrete. Just a thin layer near the surface and there also seems to be a hollow core in some parts.

      Unless the design called for this (I doubt it), it is very likely that there was some 'optimization' going on during construction. After all, rebar is expensive and concrete costs money.

    15. Re:The other mistake by Anonymous Coward · · Score: 3, Interesting

      It's been a lot of years since engineering school, but I seem to recall the recommended safety margins for most things were 100%-500%, so yes, a 20% weakening causing collapse would be a symptom of serious under-engineering.

      IAAME (I Am An Mechanical Engineer). For civil engineering projects, a safety factor of 3 to 4 would be normal and more than likely would be documented

      However, Wikipedia says this bridge is 51 years old, and that engineers have been expressing concern over its safety since the early 90s, with numerous other static and dynamic weaknesses being uncovered over the years, due to both degradation, and weakness in available computer modeling in the 60s.

      Years after it was built, the DESIGNER of the bridge expressed concerns about its safety. Because of pollutants in the air, the weather pattern around the bridge, and the unique design of the bridge, he specifically said that corrosion on its parts was greater than he had observed in other bridges of this same design. HE warned that they really needed to watch this bridge closely for corrosion problems. And because of the lack of computer modeling, that normally causes good engineers (which I believe the bridge designer to have been) to over specify the safety factor. I think this is a clear case of the authorities not doing maintenance on a bridge that clearly needed extra maintenance and it just caught up to them. Gordon

    16. Re:The other mistake by MightyYar · · Score: 2

      Yeah, the design's use of prestressed concrete cables with zero redundancy is borderline baffling. It's a visually stunning design (especially given the era), but come on! I've also never seen suspension bridge (ok, technically cable-stayed bridge) where they span two suspended portions with nothing but a more-or-less standard concrete segment. Maybe this was common at one time, but most of the recent ones seem to overlap the stays.

      --
      W..w..W - Willy Waterloo washes Warren Wiggins who is washing Waldo Woo.
    17. Re:The other mistake by SGDarkKnight · · Score: 1

      After a quick search on the bridge history, you'll see the original engineer (Riccardo Morandi) wrote about the corrosion back in 1979 and warned that it would need maintenance soon due to the sea air and pollution from a nearby steel mill.

      This was the city's own fault for not following up with it for over 40 years.

      --

      ...A no smoking section in a restaurant is like having a no peeing section in a swimming pool...
    18. Re:The other mistake by ItsJustAPseudonym · · Score: 1

      The Five Star Movement’s leaders, who now run Italy, actually cracked jokes about warnings that this bridge might collapse at regular intervals...

      Links, please?

    19. Re:The other mistake by Solandri · · Score: 2
      Engineering safety margins (you calculate the maximum stresses, figure out how string the structure would need to be to withstand it, then build it x times stronger) are typically:
      • Missiles and experimental aircraft - 1.1 to 1.25x
      • Aircraft carrying passengers - 1.5x
      • Boats - 2.0 to 2.5x
      • Cars - 3x
      • Static structures like buildings - 10x

      These are general rule of thumb. Specific parts may have higher or lower safety margins depending on how predictable or unpreditable the stresses will be. I would imagine bridges fall under the same category as buildings. Although suspension bridges have always been a bit of a balancing act between weight and strength. Some quick googling suggests the safety margin for the suspension elements is typically 2.0 to 4.0.

      Also, if you're using metal, corrosion is inevitable. Even stainless steel will corrode (it called stainless, not stainnever). You need to adhere to a strict regimen of inspecting the metal parts for corrosion and protecting it painting, lubricating, replacing). It sounds like this bridge used pre-stressed concrete stays instead of metal wire stays. Concrete is extremely strong in compression, but weak in tension. If you pre-compress it with metal rebar, that can make it usable in tensile applications where you normally wouldn't think it would work. Basically, the rebar is pulling the concrete in compression more than the load is pulling it in tension, so the concrete remains in net compression and doesn't fall apart. But that balancing act between tension and compression is highly dependent on the metal rebar suffering minimal corrosion and retaining its strength.

      Tempered glass is another example of how pre-stressing a fragile material to keep it under compression can make it stronger (strong enough to survive being shot by a bullet).

    20. Re:The other mistake by fph+il+quozientatore · · Score: 2

      They took it offline now (surprise!), but it's still available in the Internet Archive. Google-translated version: https://translate.google.com/t... "We are then told, in turn, the tale of the imminent collapse of the Morandi Bridge"

      --
      My first program:

      Hell Segmentation fault

    21. Re:The other mistake by omfglearntoplay · · Score: 1

      Bridges are ugly already... sad that somebody would risk killing people to make something ugly slightly less ugly.

    22. Re:The other mistake by pilaftank · · Score: 5, Informative

      It was designed by Calatrava

      The Ponte Morandi bears the name of its designer:
      Riccardo Morandi

      "Bridges by Morandi have proved to require extensive maintenance and repairs over the years to pass bridge safety inspections. The third span of Ponte Morandi collapsed in Genoa, on 14 August 2018, causing 43 fatalities."

      --
      dna.js
    23. Re:The other mistake by Hoi+Polloi · · Score: 2

      I think it was already accelerated at about 9.8 m/s^2

      --
      It is by the juice of the coffee bean that thoughts acquire speed, the teeth acquire stains. The stains become a warning
    24. Re:The other mistake by bobbied · · Score: 2

      I think it was already accelerated at about 9.8 m/s^2

      Given the gravity of the situation, I believe you are right.

      --
      "File to fit, pound to insert, paint to match" - Aircraft Maintenance 101
    25. Re:The other mistake by presidenteloco · · Score: 1

      What were the error bars on the 20% estimate in the engineering study?

      Could have been 20% plus or minus 10% or something like that.

      --

      Where are we going and why are we in a handbasket?
    26. Re:The other mistake by SigmundFloyd · · Score: 1

      The Five Star Movementâ(TM)s leaders, who now run Italy, actually cracked jokes about warnings that this bridge might collapse at regular intervals since the first warnings in 2012 or 2013.

      Have you got a source for this?

      --
      Knowledge is power; knowledge shared is power lost.
    27. Re:The other mistake by arglebargle_xiv · · Score: 2

      The Full Calatrava gives all the gory details. To his credit, it does list one single project that didn't go over budget or fail. However, although the Ponte Morandi is worthy of the likes of Calatrava or Frank Lloyd Wright, just the name "Ponte Morandi" tells you it was a Riccardo Morandi design, and he's no Calatrava. He's also been safely dead for several decades, so he can't be sued.

    28. Re:The other mistake by ebvwfbw · · Score: 1

      That was months before. Who knows what it was when it failed. Sometimes when things start corrode they take off like crazy. That's why preventative maintenance is important.

    29. Re:The other mistake by Agripa · · Score: 1

      I've also never seen suspension bridge (ok, technically cable-stayed bridge) where they span two suspended portions with nothing but a more-or-less standard concrete segment. Maybe this was common at one time, but most of the recent ones seem to overlap the stays.

      The concrete segment is a box girder albeit a very flat one. You may have seen similar spans where the traffic is inside of the box girder instead of on top but they are the same thing.

    30. Re:The other mistake by MightyYar · · Score: 1

      I did not know they were box girders. It's not their use of a box girder that is unusual, it's how there are three cable-stayed sections with no overlap in stays. Not only is there no overlap, they bridge the section between cable-stayed sections with these freestanding concrete sections. If you do a Google search for cable stayed bridge, you will see almost all of them with more than one cable stayed section have significant overlap between stayed sections, or the part that it bridges is much smaller than what you see here. There was a very high proportion of non-stayed to stayed deck in this bridge.

      --
      W..w..W - Willy Waterloo washes Warren Wiggins who is washing Waldo Woo.
    31. Re:The other mistake by Agripa · · Score: 1

      I did not know they were box girders. It's not their use of a box girder that is unusual, it's how there are three cable-stayed sections with no overlap in stays. Not only is there no overlap, they bridge the section between cable-stayed sections with these freestanding concrete sections. If you do a Google search for cable stayed bridge, you will see almost all of them with more than one cable stayed section have significant overlap between stayed sections, or the part that it bridges is much smaller than what you see here. There was a very high proportion of non-stayed to stayed deck in this bridge.

      I have seen them at either end of suspension bridges which use riveted girders. I suspect in this case it was done to add expansion joints between the cable stayed spans.

    32. Re:The other mistake by MightyYar · · Score: 1

      Yes, but typically a suspension bridge has giant anchorages at the end. In this Italian design, it looks like the towers are free-standing (aside from the trivial amount of rigidity added by the concrete sections with expansion joints). I'm sure the math all worked out, but it does stand out in the design. I suppose it let them use lower towers to span the same distance.

      --
      W..w..W - Willy Waterloo washes Warren Wiggins who is washing Waldo Woo.
    33. Re:The other mistake by SigmundFloyd · · Score: 1

      Of course not. Trolls don't have sources.

      --
      Knowledge is power; knowledge shared is power lost.
  2. private owned toll road the profit lost from an sh by Joe_Dragon · · Score: 1

    private owned toll road the profit lost from an shutdown is to high just fix in place.

  3. Re:That makes sense by jiriw · · Score: 2

    Unless the bridge was already built less strong than specified and the extra 20% was just the tipping point, or there were other factors involved that made the bridge collapse...
    Another example: In Italy, many things are built outside specification due to mafia involvement... because taking shortcuts made it possible to pocket construction money. I'm not saying it happened here but it's just to give you another possibly 'far fetched' explanation.

    You shouldn't put the blame on someone specific (also named: scapegoating) unless research into this catastrophe has a chance to finish and hopefully will find out what really happened... And lets pray that can be done without politics involved because this collapse already seems to be a highly laden subject in that regard.

  4. Re:That makes sense by JaredOfEuropa · · Score: 1

    it's the people who estimated the strength loss factor, not the people who did nothing once they found out.

    They both failed at their jobs resulting in loss of life, by the sound of it. And maybe both will see jail time; after all Italy prosecuted a couple of geologists for failing to predict an earthquake.

    --
    If construction was anything like programming, an incorrectly fitted lock would bring down the entire building...
  5. Italian Engineering by ArchieBunker · · Score: 1

    Beautiful but also fragile. See Ferrari or Lamborghini.

    --
    Only the State obtains its revenue by coercion. - Murray Rothbard
  6. Re:That makes sense by lgw · · Score: 4, Informative

    If the bridge was only over-engineered by 20%, then it would be a disaster to keep using it.

    It seems like the engineers have been opposed to this bridge design from the beginning, pointing out the impending disaster since 2012, and advising limiting traffic and building an alternate route. But good luck getting politicians in a democracy to spend money on infrastructure (even when given money by the EU specifically for infrastructure).

    --
    Socialism: a lie told by totalitarians and believed by fools.
  7. Re:That makes sense by Immerman · · Score: 2

    It was an old bridge (circa '67), with lots of other problems too - including the fact that traffic had quadrupled since it was designed. Engineers have been expressing concerns since the 90s. And witnesses say it was also struck by lightning just before collapsing. So it wasn't a simple matter of just corrosion-weakened cables.

    But yes, if it was only over-engineered by 20% it would have collapsed decades ago.

    --
    --- Most topics have many sides worth arguing, allow me to take one opposite you.
  8. Bridge engineers always consider overload by SuperKendall · · Score: 2

    Itâ(TM)s not just that, the bridge was hopelessly overloaded by traffic.

    Have you ever driven in New York City? Every bridge is totally full of traffic nearly 24x7, during rush hour basically parked (it took me an hour once to cross George Washington bridge leaving NYC near rush hour). That happens every day, including in driving rainstorms... bridges are usually built assuming the bridge is packed with trucks, during the worst storm imaginable (including many feet of snow, far worse than rain), then use safety margins well beyond that. It seems the designers of this bridge cut some corners.

    --
    "There is more worth loving than we have strength to love." - Brian Jay Stanley
    1. Re:Bridge engineers always consider overload by PrimaryConsult · · Score: 1

      The lower level of the GWB was originally designed to hold trains. I'd imagine it's safer to be in a completely stopped traffic jam on that bridge than it would be standing on an arbitrary piece of land.

    2. Re:Bridge engineers always consider overload by Freischutz · · Score: 4, Interesting

      Itâ(TM)s not just that, the bridge was hopelessly overloaded by traffic.

      Have you ever driven in New York City? Every bridge is totally full of traffic nearly 24x7, during rush hour basically parked (it took me an hour once to cross George Washington bridge leaving NYC near rush hour). That happens every day, including in driving rainstorms... bridges are usually built assuming the bridge is packed with trucks, during the worst storm imaginable (including many feet of snow, far worse than rain), then use safety margins well beyond that. It seems the designers of this bridge cut some corners.

      I’ve driven in all kinds of places. However, the real question is: Have you ever observed the dysfunctional cocktail of corruption, populism and incompetence otherwise known as Italian politics at work? In this case you have a steadily deteriorating bridge whose load carrying capacity is rapidly decreasing, that may not have been built to specs in the first place due to corruption and that was being subjected to traffic loads and thereby vibrations that its decayed structure could not handle. And the whole time there is a political cat fight going on with a bunch of populists wingnuts who are blocking the replacement bypass project, staging protests against any repair work and ridiculing anybody who spoke out about the danger of the situation. The bottom line is that this bridge should have been replaced and decommissioned at least ten years ago.

    3. Re:Bridge engineers always consider overload by GoTeam · · Score: 1

      Not sure about the Japanese steel company, but the company providing the wires for the Brooklyn bridge was sending faulty wires for construction: https://www.jamesmaherphotogra.... (search that page for faulty) Although I didn't see it listed in the article I provided, I believe the company providing the wires would send a spool of wire for inspection (that they had purchased from a company that made good wire). Once that spool passed, they would accept all the wire in that load for bridge construction. They'd then divert the spool of good wire and use it for inspection the next time they delivered a batch.

    4. Re:Bridge engineers always consider overload by SuperKendall · · Score: 1

      Iâ(TM)ve driven in all kinds of places. However, the real question is: Have you ever observed the dysfunctional cocktail of corruption, populism and incompetence otherwise known as Italian politics at work?

      That's why I mentioned NYC - maybe corruption is worse in Italy than NYC, but honestly it would take more convincing,

      --
      "There is more worth loving than we have strength to love." - Brian Jay Stanley
    5. Re: Bridge engineers always consider overload by arglebargle_xiv · · Score: 1

      I think the OP was referring to George Washinton. OTOH he never needed any bridges.

    6. Re:Bridge engineers always consider overload by danbert8 · · Score: 1

      Yep, but when it was discovered the added an additional safety factor on top of what they had already and the cables are probably way over conservative now. Which probably is why the Brooklyn Bridge is still standing and probably will for another century.

      --
      Yes it's an anecdote! Were you expecting original research in a Slashdot comment?
  9. Re:That makes sense by lgw · · Score: 5, Insightful

    They both failed at their jobs resulting in loss of life, by the sound of it.

    If by "failed" you mean "consistently warned about the impending disaster for the past 6 year, while politicians openly mocked the warnings", then sure.

    And maybe both will see jail time

    Probably so. It's not like the politicians who blocked funding of an alternate route are going to let any consequences affect themselves.

    --
    Socialism: a lie told by totalitarians and believed by fools.
  10. Re:private owned toll road the profit lost from an by Anonymous Coward · · Score: 1

    The main reason for government to privatize anything is to help their non-government corporate friends make tax-payer money. The second reason is so that when shit inevitably happens due to all the profit taking instead of maintenance, the government can pass the blame out of government so their political greedy ass can keep it's 'job'.

  11. Corrosion on I-278 in Brooklyn by michaelmalak · · Score: 1
  12. re: cutting corners by King_TJ · · Score: 3, Informative

    One article I read said there was a good likelihood the bridge was constructed using less concrete than specified, because the mafia was heavily involved in bidding for these projects at the time. One of their favorite ways to win low bids for construction was skimping on the concrete used.

  13. Can we stop judging before proper investigation? by kiviQr · · Score: 1

    Twitter will not solve the "mistery" - a proper investigation will do. I know it will take time but at least it will cut sensationalism. Just give it a time.

  14. I-35w bridge collapse was USA's wake-up-call! by Joe_Dragon · · Score: 2

    I-35w bridge collapse was USA's wake-up-call!

  15. Corrosion problems on Forth Road Bridge in Scotlan by Pop69 · · Score: 3, Interesting

    When they identified corrosion problems with the main cables on this bridge, they installed dehumidifiers for the cables. They also built a replacement bridge and now use the older bridge as a public transport route, a traffic level it can easily cope with. Perhaps this should have been done with this bridge too ?

  16. Re: cutting corners by SuperKendall · · Score: 1

    One article I read said there was a good likelihood the bridge was constructed using less concrete than specified

    Sad if so - you'd really hope there would be final checks in place to prevent things like that from crippling a major building project!

    --
    "There is more worth loving than we have strength to love." - Brian Jay Stanley
  17. 20% strength reduction from what? by hey! · · Score: 1

    So the bridge is 0.8 * X strong. How big is X? How big did X need to be?

    A two-fold factor of safety is normal in projects like this, so if the bridge is 0.8 * X strong, it should still be 60% than it needs to be. And civil engineers tend to be a cautious lot; after several rounds of review of something like a bridge it tends to end up grossly over-designed as each engineer adds an additional margin of safety to the prior engineer's work. So there should be no way that a bridge that has lost 20% of its strength is dangerous.

    So this raises a number of questions. Did the inspectors miss something? Was the bridge improperly designed for the load it was carrying? Was it not built according to the design? Those are all possibilities. It could be a combination of them.

    The Kansas City Hyatt pedestrian bridge collapse was due to two factors. First, the original design did not meet building codes; but even so the design should have been able to support as many people on the bridge as could fit. Second, changes were made to the design as the bridges were constructed, such that the bridges could barely support their own weight. Now had the original design been as strong as the code called for, the disaster wouldn't have happened. Had it been built to the original, inadequate design, the disaster wouldn't have happened.

    The point is disasters can be complicated affairs involving many errors. While in this case the rust no doubt contributed to the failure, it may not be the only thing that went wrong.

    --
    Post may contain irony: discontinue use if experiencing mood swings, nausea or elevated blood pressure.
    1. Re:20% strength reduction from what? by jbengt · · Score: 1

      A two-fold factor of safety is normal in projects like this, so if the bridge is 0.8 * X strong, it should still be 60% than it needs to be.

      Margins of safety and safety factors are used for several good reasons, and are used to account for aging, because of idealizations used in the calculations, or because of other uncertainties. If you think that it's OK to be below the safety factors, you're thinking wrong. Anyway, according to TFA:

      Espresso reporter Fabrizio Gatti told SKY TG24 that a 20 percent reduction in strength would not be significant in a modern bridge, but on a structure with the known defects of the Morandi Bridge it should have merited swifter, more decisive action.

    2. Re:20% strength reduction from what? by hey! · · Score: 1

      What I'm saying is that it depends on context. Nonetheless, if a 20% reduction in strength caused the bridge to fail catastrophically, then the bridge was unsafe at full strength.

      --
      Post may contain irony: discontinue use if experiencing mood swings, nausea or elevated blood pressure.
  18. The problem was known much earlier by mi · · Score: 4, Informative

    The bridge's sorry state was known years ago. A certain political party used the "environmentalist" demagoguery to keep the status quo.

    And now the same people are blaming the company that built and maintained the structure:

    Transport Minister Danilo Toninelli, a member of the governing Five Star Movement (M5S), called for the immediate resignation of the company's top management Wednesday.

    "First of all the top executives of Autostrade have to resign," he said in a message on Facebook. "If they can't manage the motorways, then the state will do it."

    Because the government is so good at everything...

    --
    In Soviet Washington the swamp drains you.
  19. Nah! by mschaffer · · Score: 1

    It's much more fun to jump on the bandwagon then to heed reason and empirical observation.

  20. Re:That makes sense by Nidi62 · · Score: 1

    There's a recent case in Spain where some rapists got out of jail after a few months because their lawyers are appealing the verdict and it would just be too cruel to keep convicted rapists in jail while the appeal drags on.

    Were they granted bail going into the trial? If so, it seems reasonable to me that if the defendant was eligible for pre-trial bail then that bail should be extended for an appeal. Reduces the chance that someone innocent spends time behind bars. Of course on the other hand they also miss out on time served if they are guilty.

    --
    The only thing necessary for evil to triumph is for it to be pitted against a slightly greater evil
  21. Re:That makes sense by angel'o'sphere · · Score: 1

    Step-dad got 10 years. Mom got about 12. Pedophile dude got about 10. And Germany says these sentences are "really long".
    Considering that a human being lives about 80 years, yes, that is really long.

    I'm sure about halfway through, at most, the legal system will start to feel sorry for them and they'll start getting weekend releases and so on.
    And what is wrong with that? Revenge very much?

    --
    Cost free eBook I read (by iBook/Kobo/Amazon/ObookO/Gutenberg etc.): "The Green Odyssey" by Philip Jose Farmer.
  22. Re: cutting corners by Anonymous Coward · · Score: 1

    The final checkers would be threatened or bribed.

  23. Re:That makes sense by JaredOfEuropa · · Score: 1

    Please read the original post: "the people who did nothing once they found out". Those are the ones who failed. Not the people warning about the issues with that bridge, but the people ignoring those warnings.

    --
    If construction was anything like programming, an incorrectly fitted lock would bring down the entire building...
  24. Re:That makes sense by Interfacer · · Score: 1

    Just a wild guess: you think that the US style federal prison, with gang rape, extortion, and senseless violence is just what the doctor ordered?

  25. Reduce speed? by superdave80 · · Score: 1

    ... or reduce the speed"

    I'm having trouble figuring out how a reduce speed would reduce the load on a bridge. Anybody have an idea how that works?

    1. Re:Reduce speed? by ebvwfbw · · Score: 1

      Flex. Bridges bend. So do the things on it. Gives it more time to adjust. This isn't that much of a big deal generally. There is also side load. If everything is going straight then that's fine. It's when you have a semi or some other big load and they change lanes. So you're talking say 80,000 Lbs for a fully loaded semi and now you want to move it say 20' to the right or left. Something has to exert that pressure on it. If you're going slow it's not so bad. You're still going up and down for the most part. Going fast and now you have a side load to deal with. Exceed the capacity of whatever it is holding you up and you have a failure. People have a bad day.

  26. Re:That makes sense by SigmundFloyd · · Score: 1

    after all Italy prosecuted a couple of geologists for failing to predict an earthquake.

    This bullshit again? They were prosecuted for saying there was no risk and that people should go back home.

    --
    Knowledge is power; knowledge shared is power lost.
  27. Re: cutting corners by arglebargle_xiv · · Score: 1

    This is what an earlier poster was referring to with the observation that "the construction companies made some 'equivalent substitutions'". These sorts of shenanigans are SOP in Italian civil works projects, you just get used to it after awhile.

  28. Re: That makes sense by Anonymous Coward · · Score: 1

    Sure. In the meantime, let's just dismantle the EU which takes away Italy's own money, and leave it to the Italians. Then, and only then, if they won't use it to maintain their infrastructure, they'll be the ones to blame.

  29. Re:Italy and India by ebvwfbw · · Score: 1

    Really? I thought Italy was the Italy of Europe.

  30. That's paranoia and too much faith in planning by presidenteloco · · Score: 1

    The universe is entropic (tending toward higher entropy - lower organization)

    Stuff breaks down.

    You don't need to plan to have things fail. They will fail by default.

    All you need is insufficient planning, budget, and execution of how to make them last unexpectedly long.

    --

    Where are we going and why are we in a handbasket?