Project Management For Programmers?
welshdave asks: "I'm a senior web developer in a medium sized company where the project managers have no programming experience of any sort. I'm of the opinion that project managers should understand the projects that they're managing and want to move into project management myself. I'm aware that I may meet resistance from the current project managers - many of them have been hired with no previous experience of anything. Previous suggestions to senior management that myself and other developers would feel better with a technical person running projects have been dismissed. As a result we are routinely told to skip testing or to implement the impossible, with an emphasis on how things look rather than how well things actually work. Has anyone else found the barrier to project management is their technical knowledge. How did you get past it?"
I found that it was easier to sit down with my PM and asked then the one thing they needed to make their job easier. If it was half way reasonable I went out of my way to give that to them ... in turn they seemed more willing
to listen to reason and help form a project
timeline that was 1/2-way based on reality.
chongo (was here)
As a developer I've found that most management-types don't give a hoot about technical details, or much of anything else that a heads-down developer might care about.
What will get attention is an understanding of business need, an attention to detail in terms of reporting progress and delivering systems that work, and positive attitude.
As a manager I get very tired of hearing about the programmers, sysadmins, etc. complaining that such-and-such can't be done, or otherwise blocking progress. Much more often than not things that "can't be done" just require a re-statement of the problem and some creative application of simple ideas.
My recommendation would be to make a friend or at least the aquaintance of one of the project manager's bosses, and just talk. Don't attack the current project managers style -- that would make their boss look bad. Don't complain about the impossibility of whatever. Mention that you have an idea of how to accomplish some objective. Show that you have some clue as to what the managers are interested in. Show that you have some interest in the companies performance. Be prepared to give out some 'write ups' that show a very clear train of thought and that make a clear recommendation up front, with backup material and dialogue exploring alternatives explaining why the recommendation makes sense.
If that doesn't work, then get a job with a company that has a clue. They're out there.
"But actually trying to use m4 as a general-purpose langage would be deeply perverse" --ESR
Good project managers need a different set of skills than system architects. Project managers think in terms of timelines, tasks and dollars. Architects think in terms of system components, their interactions, user requirements and technology. While there are some people who can do both well, they are quite rare as they require fairly different ways of thinking.
Anyway, I'll bet dollars to donuts that the resistance you face from upper management has more to deal with the fact that you put the system before the company. They want project managers that put the company (or client) first. Big suprise, eh? If you want to lead projects, explain how you (or rather, people like you) can help the company make more money or make the client happier while spending the same amount of money (which, should lead to more money for the company). It's pretty much as simple as that. Cheers
One thing both you and the project manager need to understand is:
;)
The project manager deals with the business side of things.
The technical lead deals with the technical side of things.
So while he may be setting (or have forced upon him) aspects such as deadlines, you need to control scope, methodology and quality. Communicate with him constantly. Imply (if not state explicitly) that you need to work on resource allocation, something he may be trying to plan for you right now. to have everything stated down on paper is best for both of you, you can at least then agree or disagree and sort things out.
It may also help to implement a proper development strategy you can agree on - if he won't listen, just escalate the issue. One that is tried and tested is a good bet, whether it's Extreme programming (a good suggestion) or something coming from the business side of things.
Whichever it is, the problem here seems to arise from a lack of definability of responsibility and roles, and that's what needs to be set and agreed upon so you can both do your job properly! He's probably as exasperated at you at the moment
Fross
(a technical architect working as a project manager!)
I've had managers before that varied from well experienced, technically, to not at all. Rarely was I asked to perform the impossible. And in those cases where it was impossible, it really was impossible. I simply pointed this out to the manager ... and I explained in detail why that was the case. In all cases things got corrected. Maybe I'm not so closed-minded as some techies out there, and I know most everything is possible. The better managers I found came to me with the ideas of what they were considering doing, and asked me to prepare a report on the feasibility and costs (mostly in hours of work) of doing it. I usually included an impact analysis as well. But you can be sure that if I tell my manager that it is impossible, then it really is impossible. Usually the truth is "it'll cost ya". Maybe techies need to learn to say that more often.
now we need to go OSS in diesel cars
Until recently, I was the development manager at a fairly large internet company; we had project managers who knew very little about software development, database design or how to run software projects. Do you know why ? because that was my job.
Whatever you may think, technology is not the most important part of the project - delivering what the business wants and making the right trade-offs to get that done is what matters. The intellectual purity of our great code is wonderful, but who cares if it gets delivered 6 months after it's needed ?
The project manager's job is to work out what needs to get built and by when; they need to get all the external dependencies sorted out, ensure the requirements are either known or the person(s) who controls those requirements is available when required, get the money and resources sorted out, and work with a techie on how to get the deliverables built in time.
I was that techie - and it worked pretty well. The project manager asks for stuff by a certain date, I work with the rest of the team to see what we'd need to do to make that happen, I negotiate with the PM on what is and is not in scope, and get the techies to start with whatever needs to happen to get the project done.
Every couple of days, I sit down with the Project Manager to agree out where we are, re-negotiate dates/resources etc. if required, assess new requirements, maybe work out in more detail what the plan for the next phase looks like. If we have to cut corners - and this does happen, coz we don't live in a perfect world - I work with the developers to see what we can cut that will have the least effect on the quality - the PM doesn't make that call, I do.
Project Management requires skills I don't have - I don't understand the commercial pressures on the company, I don't understand the legal framework we're working in, I don't have the patience to build and update Gantt charts, I don't enjoy endless meetings or chasing people for every little detail of their deliverabes. The project managers know this - they don't think any less of me, just as I respect the fact they couldn't design a database schema to save their lives.
So, I would suggest trying to form a good working relationship with your project manager by trying to understand what they do for a living, understand that there is more to a project than the technical deliverables, learn to speak their language, and offer alternatives when they ask for the impossible.
The attitude of most of the posts in this subject has been "huh, we're 200 times smarter than those idiots running the project, they're so stupid they couldn't blah blah blah". Hey, if you're so smart, it's your job to use that intellgence to move the project forward, not whine about how what a bad job everyone else is doing.
It's all very well in practice, but it will never work in theory.
Has anyone else found the barrier to project management is their technical knowledge. How did you get past it?
Absolutely not. Although I have suffered the problems you mention.
I have found that these are more often due to poor communication between PM and coder. It's the PM's job to direct the project to a successful completion while keeping an eye on resource allocation. It is the techie's job *clearly* explain the technical restrictions and options.
If you are relying on one team member to have *all* the necessary skills, then you do not have a real "team".
I am a Karma Library.
I miss my PM. Her job was basically:
When prototypes for the project were running late, I didn't have to spend endless hours chasing people down and tracking the issues delaying them. My PM did that.
When the project had slipped 6 weeks, I wasn't the one on the calls getting yelled at and yelling back about the fact that more than 50% of the TYPES of prototypes we needed hadn't even been delivered yet. My PM did that. I was down in the lab working.
When I had to attend technical calls ( like bug scrubs ) I didn't have to go dig up the bugs being covered so I could review them for the meeting. My PM always met with us 30 minutes prior and went over the list so that we could get things clearly in mind going into the call.
And when the shit hit the fan, and we were death marching till 2am for weeks on end, my PM was there making sure we got fed ( on the company dime ), and staying late to make sure we did eventually go home and sleep.
None of this really requires much technical skill on the part of the PM. All it requires is a respect for the team and an understanding that the most effective way to get your project in on time is to support the team. By the middle of the project we ( the technical guys ) where willing to kill ourselves to meet the project objectives for this PM.