Incorrectly Built SLS Welding Machine To Be Rebuilt
schwit1 writes A giant welding machine, built for NASA's multi-billion dollar Space Launch System (SLS), has to be taken apart and rebuilt because the contractor failed to reinforce the floor, as required, prior to construction: "Sweden's ESAB Welding & Cutting, which has its North American headquarters in Florence, South Carolina, built the the roughly 50-meter tall Vertical Assembly Center as a subcontractor to SLS contractor Boeing at NASA's Michoud Assembly Facility in New Orleans.
ESAB was supposed to reinforce Michoud's floor before installing the welding tool, but did not, NASA SLS Program Manager Todd May told SpaceNews after an April 15 panel session during the 31st Space Symposium here. As a result, the enormous machine leaned ever so slightly, cocking the rails that guide massive rings used to lift parts of the 8.4-meter-diameter SLS stages The rings wound up 0.06 degrees out of alignment, which may not sound like much, "but when you're talking about something that's 217 feet [66.14 meters] tall, that adds up," May said.
Asked why ESAB did not reinforce the foundation as it was supposed to, May said only it was a result of "a miscommunication between two [Boeing] subcontractors and ESAB."
It is baffling how everyone at NASA, Boeing, and ESAB could have forgotten to do the reinforcing, even though it was specified in the contract. It also suggests that the quality control in the SLS rocket program has some serious problems.
ESAB was supposed to reinforce Michoud's floor before installing the welding tool, but did not, NASA SLS Program Manager Todd May told SpaceNews after an April 15 panel session during the 31st Space Symposium here. As a result, the enormous machine leaned ever so slightly, cocking the rails that guide massive rings used to lift parts of the 8.4-meter-diameter SLS stages The rings wound up 0.06 degrees out of alignment, which may not sound like much, "but when you're talking about something that's 217 feet [66.14 meters] tall, that adds up," May said.
Asked why ESAB did not reinforce the foundation as it was supposed to, May said only it was a result of "a miscommunication between two [Boeing] subcontractors and ESAB."
It is baffling how everyone at NASA, Boeing, and ESAB could have forgotten to do the reinforcing, even though it was specified in the contract. It also suggests that the quality control in the SLS rocket program has some serious problems.
"and not micromanage it". That's the rub. The micromanaging, the reporting and compliance costs, can be over 50% of the cost for some federal contracts, but most of the time that's required by thousands upon thousands of pages of federal law. When you have a comoany that knows how to do a certain thing , aka one of those evil corporations, getting hired by the federal government, some people want to do a lot of paperwork and stuff to keep track of what's going on, and other people go crazy with it. The organization I work for used to do a lot of federal contracts. We quit and now just do state contracts for states that are reasonable.
Still other people added a bunch of requirements for federal contracting that aren't really relevant to the project. For example, how many black women work for each of your major suppliers? How much do your interns make? Are all of the web pages and documentation you've ever made fully accessible to people who are both blind and deaf?
We quit dealing with the feds and certain states because it's just not worth it. It would cost SPACEX five times as much to build a federally-contracted rocket than it costs to build their own.